What is the role of the contract administrator under a JCT contract?
What if a contractor does not comply with an instruction on a JCT contract?
Do you even know how an employer’s agent role differs from a contract administrator role?
EA is seen as a client’s advisor and is required to protect the client’s interests whereas the CA must act impartially when administering the contract, even if this means that the decision is not in the best interest of the employer
What status does the programme have under a JCT contact?
What is practical completion?
Do the works have to be totally completed before practical / section completion is achieved?
Can the PC certificate be rescinded once issued?
No
what is a non-completion certificate?
Issued by the CA to certify that the works / section has not been completed by the contractual completion date
What are the consequences of a non-completion certificate?
The employer has the right to withhold liquidated damages (A pay less notice is also required)
When PC is issued, what are the consequences?
If the contract administrator believes completed work is not in accordance with the contract, what can they do to clarify?
They can issue an instruction for the opening-up and inspection of covered work, materials or goods of the testing of work, materials and goods to determine if they are in accordance
Who bears the costs of opening and testing?
The cost is added to the contract sum unless the work is not in accordance
What is the definition of an extension of time?
What is the procedure for claiming an extension of time?
What are the time periods related tot granting extensions of time?
Why have an extension of time?
Does an extension of time automatically give contractor the right to apply for additional prelims?
No