Who is responsible for administering the building contract?
Please detail some key responsibilities of the contract administrator under a JCT contract?
How does the EA role differ from the CA role?
CA - solely responsible for administering contract for the employer. Impartial role in the contract
EA - acts on behalf of the employer in all matters. When carrying out certification and decision-making, EA should still act impartially
What is practical completion?
Can you rescind the PC statement once it has been issued?
No - once issued, it’s final and binding on the employer
What are the consequences for the contractor and employer once the PC statement has been issued?
What is a non-completion certificate?
What are the consequences of a non-completion certificate?
Triggers right for employer to levy liquidated damages if they choose to do so (employer must also write to contractor notifying them of intent and issue pay less notice to recover LDs)
If a project was due to finish before Christmas, but an extension of time was given which meant the contractor finished after Christmas, is the contractor entitled to costs over the Christmas break, which is normally 2 weeks?
What is the defects liability period?
What’s your understanding of latent defects and what contractual issues are associated?
What should the CA do if latent defects are discovered?
Issue instruction to contractor as necessary, may include to instruct compliance with 3rd party examining / opening up works to identify defect
Why might the EA instruct the contractor to ‘open up’ works which have been covered up?
When issuing instructions for further opening up and testing to determine the extent of non-compliance what sort of things should the CA consider?
Assuming the EA has instructed the contractor to ‘open up’ the works, what are the potential outcomes? (including effect on cost and completion date)
If the works or materials aren’t in accordance with the Contract, what options does the Architect have available to them?
Architect may:
- Instruct contractor to remove all defective work / for variations necessary, materials and goods at their own expense and time
- Notify in writing they can remain with appropriate deduction made from contract sum
- Instruct to open up and test further work to determine extent of any non-compliance
What is an EoT?
Extension of time - provision allowing CA to adjust completion date, so postponing employer’s right to recover liquidated damages. Used in instances where delay is not contractor’s responsibility or fault
What’s the procedure for claiming an EoT?
From a CA point of view, what are the time periods related to assessing relevant events and adjusting the completion date?
CA must notify contractor of their decision within 12 weeks of receipt of the required particulars (sooner if completion date less than 12 weeks away) and state extension awarded
If the contractor successfully demonstrates a relevant event and CA adjusts the completion date, is the Contractor due additional preliminaries?
No, Contractor is required to demonstrate a ‘relevant matter’ for L&E claim
Would you as the QS get involved in helping the CA assess EoT?
Yes, involved in assessing financial implications of EoT, if applicable
How did you assess an EoT claim on xxx project?
How would you deal with an urgent Verbal Instruction?
How is completion defined under NEC ECC contracts?
Clause 11.2(2)
NEC3
- Done all work which Works Information states they are to do by Completion Date and
- Corrected notified Defects which would have prevented the Employer from using the works and Others from doing their work
NEC4
- Done all the work the Scope says to be done by Completion Date and
- Corrected notified Defects which would have prevented the Clieent using the works or Others from doing their work