What is the role of contract administrator under a JCT contract?
What if a contractor does not comply with an instruction on a JCT contract?
Do you know how an employer’s agent role differs from a contract administrator’s role?
EA is seen as a client advisor and is required to protect the client’s interest whereas the CA must act impartially when administering the contract, even if this means that the decision is not in the best interest of the employer.
What is practical completion?
Do the works have to be totally completed before practical / sectional completion is achieved?
It is common practice for PC to be granted when the works are substantially complete - i.e. there may be minor defects or omissions but nothing that would prevent the employer taking occupation.
Can the PC certificate be rescinded once issued?
No
What is a non-completion certificate?
Issued by the CA to certify that the works / section has not been completed by the contractual completion date.
What are the consequences of a non-completion certificate?
When PC is issued, what are the consequences?
If the contract administrator believes completed work is not in accordance with the contract, what can they do to clarify?
They can issue an instruction for the opening up and inspection of covered work, materials or goods or the testing of the work, materials and goods to determine if they are in accordance.
Who bears the costs of opening and testing?
The cost is added to the contract sum unless the work is not in accordance.
What is the definition of an extension of time?
What is the procedure for claiming an extension of time?
What are the time periods related to granting extensions of time?
Why have an extension of time?
Does an extension of time automatically give the contractor the right to apply for additional prelims?
No