What is final account?
This is prepared at the end of the works, adjusting the sum set out in the contract to take account of any variations, provisional sums, loss and expense. The account confirms the final payment required under the contract but is frequently the source of disputes between the parties.
What is another contract you have worked with?
Homeowner Contract (with Consultant) 2015 Edition for use in Scotland
Building Contract for a homeowner/occupier who has appointed a consultant to oversee the work.
Is simplified for domestic clients - less formal, plain language.
Excluded from Constuct Act - Adjudication does appply.
Lump sum, interim payments or single on completion.
Suitable for smaller domestic projects.
What are the main duties of a CA under an SBCC Minor Works Contract?
The CA administers the contract by issuing instructions, certifying interim and final payments, assessing variations, granting extensions of time, and issuing Practical Completion and Final Certificates. They also chair meetings, record progress, and ensure communication and documentation are maintained in accordance with the contract conditions.
What is the purpose of issuing contract instructions, and when should they be used?
Contract Instructions are used to direct changes in design, materials, sequence, or other matters under the contract. They ensure variations are properly authorised and recorded, maintaining a clear audit trail. They should only be issued by the CA or authorised representative and must not be retrospective.
What is the difference between Practical Completion and Final Completion?
At Practical Completion, works are sufficiently complete for occupation or use — minor snagging may remain. Final Completion occurs after the Rectification Period, once all notified defects are rectified, and the CA issues the Final Certificate, settling the account and releasing retention.
What is the purpose of retention, and how is it managed under the SBCC Minor Works form?
Typically 3–5%, retention is deducted from interim payments — half released at Practical Completion and the remainder after the Rectification Period. It incentivises completion and protects the employer against defective work.
Talk us through the variation you agreed on the boundary wall project?
This was in relation to additional sections of take down and rebuild.
This was highlighted to be on site at a section where established buddleia was being removed.
Agree the wall required take down and rebuild in that area following removal of this.
Measured on site, used tender rates, agreed cost with Contractor.
Presented information to the client, approved.
Issued written Contract Instructions. (included scope, spec (as per tender), date of agreement, cost)
What are the interim payment timescales for a SBCC minor works contract
The contract’s Interim Valuation Date determines the cycle, typically on a monthly basis, with the first IVD not more than one month after the commencement date.
The due date for each interim payment is 7 days after the IVD.
The CA must issue an interim certificate within 5 days of the due date.
Final Payment Date: Payment must be made within 14 days of the due date.
What is meant by procurement?
The overall process of acquiring construction work or services.
What are the main procurement methods?
Traditional.
Design and build.
Management contracting.
Construction management.
What is traditional procurement?
The design is completed by the clients design team before competitive tenders are invited and a main contractor is employed to build what the designers have specified.
This can be remeasureable or lump sum.
What is meant by lump sum?
A contractor is appointed for a fixed sum and with a set time period.
What should be considered for traditional procurement?
The route depends on full and complete design information which can be time consuming to prepare.
Full design might not be achievable and can lead to contractors design portions and inclusion of provisional sums. Can compromise output cost and time certainty.
What is design and build procurement?
The contractor is responsible for both the design and construction of a project.
Includes employers requirements.
The employer employs an agent to administer the conditions.
What is management contracting?
A management contractor is employed to contribute their expertise to the design and to manage construction with a management fee being paid to them.
What is construction management?
The employer places a direct contract with each of the trade contractors and utilises the expertise of a construction manager who acts as a consultant to co ordinate the contracts.
What are dayworks
Dayworks are the costs for labour, materials, and plant for work that cannot be valued through the contract’s normal pricing methods.
Work that is urgent and too complex to price upfront.
The work is documented on daywork sheets, which must be authorized by the client’s team to be paid for.
When is a SBCC minor works contract used?
The work is simple in character;
The work is designed by or on behalf of the Employer;
The Employer is to provide drawings and/or a specification and/or work schedules to define adequately the quantity and quality of the work; and
where an Architect/Contract Administrator or Quantity Surveyor, if appointed, is to administer the conditions.
Ca be used by both private and local authority employers.
Not suitable where detailed control procedures are needed or the work is to be staged.
What is nomination?
Selection of particular subcontractor to carry out works, supply or manufacture of materials?
What is a NEC Contract?
New Engineering Contract can be used within building and civil engineering projects.
What is frustration?
The automatic termination of a contract if an unforeseen event makes performance impossible, illegal, or fundamentally different from the original agreement.
What are the main parts of a minor works contract?
Recitals
Articles
Contract particulars
Conditions
Schedules
Talk us through the claim for additional prelims for the external fabric repair project?
Bavelaw Gardens. External fabric repairs, included roofing, rendering, insulation upgrading.
Minor works contract.
Contractor submitted a written notification including the reasons, impact assessment, call outs, managers etc.
The work was weather dependent. There was a number of named storms over the contract.
The asbestos although took time, did not affect the progress on site as the works proceeded elsewhere, the PC was not involved in arranging of chasing the asbestos so wasn’t valid.
Agreed reasonable but reduced their claim, this was accepted.
How did you negotiate the final account at Northumberland Street?
Prepared and reviewed relevant information. Contract instructions, financial statements.
Complex project – best to meet in person.
Methodically worked way through all info and agreed outstanding queries.
Remained professional, and listened to the PC.
Used rules of measurement as much as possible.