Contract Administration Flashcards

(114 cards)

1
Q

What is the primary function of contract administration?

A

Execution and performance of a building contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does the role of the contract administrator begin?

A

When the contract is signed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which role corresponds to the contract administrator in JCT contracts?

A

Contract administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the four key elements required to make a binding contract?

A
  • Offer
  • Acceptance
  • Consideration
  • Intent to create legal relations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does practical completion mean?

A

Works are complete except for minor defects that do not prevent use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the typical duration of the defects liability period?

A

6 to 12 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What triggers the commencement of the defects liability period?

A

Certifying completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What must a contractor do during the defects liability period?

A

Rectify defects at their own cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of the final certificate?

A

Confirms that all defects have been rectified and the contract is fully complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Under JCT, what is the CA’s responsibility regarding design?

A

The CA’s role does not include design responsibilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is professional indemnity insurance (PII)?

A

Business insurance that protects professionals against legal costs and claims for damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who typically needs professional indemnity insurance?

A

Professionals providing design, advice, or consultancy services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does professional indemnity insurance cover?

A
  • Claims of professional negligence
  • Breach of duty of care
  • Errors or omissions
  • Defamation
  • Loss of documents
  • Intellectual property infringement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What must a contractor do to request an extension of time?

A

Give written notice of the relevant event to the CA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the final account in contract administration?

A

Prepared at the end of the works, adjusting the sum set out in the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What health and safety legislation must the CA be aware of?

A
  • Health and Safety at Work etc. Act 1974
  • CDM Regulations
  • The Regulatory Reform (Fire Safety) Order 2005
  • Fire Safety Act 2021
  • Building Safety Act 2022
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are preliminaries in a contract?

A

Describes the nature of the work and general conditions for execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the difference between partial possession and sectional completion?

A
  • Partial possession: Employer takes possession of part of the building
  • Sectional completion: Defined sections are completed and occupied as per contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the purpose of retention monies?

A

Held in trust to ensure contractor completes works and remedies defects after practical completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How long must records be kept during a contract?

A

A minimum of six years or longer if signed as a deed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are variations in construction contracts?

A

Alterations to the scope of works due to changes in requirements or unforeseen circumstances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does the CA need to do when unforeseen works arise?

A

Obtain express authorization from the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What does the term ‘quantum’ refer to in the context of a contractor’s claim?

A

The financial amount of the contractor’s claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the CA’s role in site inspections?

A

Inspect the project to ensure responsibilities are discharged appropriately

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What must the CA do with materials on or off site?
Consider them during interim valuations and check for invoices or physical existence
26
What defines a Minor Works contract under JCT?
For small, simple projects typically under £250,000 in value
27
What must the client do to formally appoint a CA?
Sign written terms of engagement detailing services and fees
28
What are the three versions of JCT's Standard Building contract?
With quantities (Q), without quantities (XQ), and with approximate quantities (AQ) ## Footnote Each version is designed to meet the needs of both private and public sectors.
29
What must the client do to formally accept the CA's appointment?
Sign a set of written terms of engagement or appointment ## Footnote This document details the services to be provided, the fee basis, and the firm’s complaints handling procedure.
30
Who should be appointed in a contract to avoid issues with personal liability?
The firm rather than the individual surveyor ## Footnote This helps avoid complications related to personal liability.
31
What is a key aspect of VAT related to construction works?
It is a complex area of practice requiring specialist tax advice ## Footnote The contractor must confirm VAT rates to the CA and employer, and zero-rated work may apply.
32
What type of contract is an NEC contract primarily used for?
Construction, engineering, and infrastructure projects ## Footnote It promotes collaboration, flexibility, and proactive project management.
33
When is an NEC contract typically used?
Public sector projects, projects requiring collaboration, projects with complex risk management, design and build projects, and projects needing clear communication ## Footnote NEC is popular for government-funded projects and encourages teamwork.
34
What are common types of NEC contracts?
* ECC (Engineering and Construction Contract) * ECSC (Short Contract) * ECSS (Subcontract) * PSC (Professional Services Contract) * TSC (Term Service Contract) ## Footnote Each type is tailored to specific project needs.
35
What is a JCT contract commonly used for?
UK construction projects, especially in the building sector ## Footnote It provides a suite of standard forms of contract tailored to different project types.
36
When is a JCT contract typically used?
Traditional building projects, design and build projects, private sector projects, projects with standard risk allocation, and projects needing simplicity or specificity ## Footnote JCT contracts have well-established clauses for liability and delays.
37
What are popular JCT contract types?
* JCT Standard Building Contract * JCT Design and Build Contract * JCT Intermediate Contract * JCT Minor Works Contract * JCT Homeowner Contract ## Footnote Each type serves different project sizes and complexities.
38
What happens if the Contractor fails to comply with specific requirements causing a critical path delay?
The Contractor may be entitled to an extension of time but not to additional preliminaries costs ## Footnote Delay determination is by the Contract Administrator.
39
What is an advanced notice in payment provisions?
A lump sum paid to the contractor to assist with cashflow and provide security ## Footnote It is typically secured by a bond and equals the amount of peak cash flow.
40
What are the JCT contract types (5)?
* JCT Intermediate Building Contract 2016 (with Contractor's Design Portion) * JCT Minor Works Building Contract 2016 (with Contractor's Design Portion) * JCT Design and Building * Management Building Contract 2016 * Measured Term Contract 2016 ## Footnote None
41
What is the Management Building Contract 2016?
* Suitable for large-scale or complex projects * The employer appoints a management contractor who coordinates the construction process * The works are divided into packages carried out by different works contractors ## Footnote None
42
When should the Management Building Contract 2016 be used?
* When early start on site is needed before full design completion * When the employer wants direct control over works contractors * When flexibility in procurement and programming is essential ## Footnote None
43
What is the purpose of the Measured Term Contract 2016?
* Designed for maintenance and minor works over a period of time * Ideal for repetitive work or maintenance services over a defined term (e.g., 1–5 years) * Commonly used by local authorities, housing associations, and facilities managers ## Footnote None
44
What are the key characteristics of the Measured Term Contract 2016?
* Based on a schedule of rates rather than a lump sum * Employer issues individual instructions (works orders) * Allows for varying types and volumes of work over time ## Footnote None
45
Who are the key roles in the Measured Term Contract 2016?
* Employer: Issues works orders and manages the contract * Contractor: Carries out work as instructed * Contract Administrator: Oversees the contract and ensures compliance ## Footnote None
46
How is payment structured in the Measured Term Contract 2016?
* Based on measured quantities from the schedule of rates * Payments are made following completion of each works order ## Footnote None
47
When is the Measured Term Contract 2016 appropriate to use?
* For ongoing maintenance, repairs, or small-scale improvements * When the scope of work is not fully defined upfront * When cost control and flexibility are important ## Footnote None
48
What are the key differences between the JCT Minor Works and Intermediate contracts?
* Minor works is less detailed and prescriptive * Intermediate contract includes sectional completion provisions * Intermediate contract better sets out individual responsibilities ## Footnote None
49
What distinguishes a nominated subcontractor from a domestic subcontractor?
* Domestic subcontractor is chosen by the contractor * Nominated subcontractor is chosen by the employer * Contractor has limited control over nominated subcontractor ## Footnote None
50
What are the risks of using a nominated subcontractor?
* Limited control over selection and terms * Potential claims for loss or expense due to performance issues * Contractor may not be liable for design issues or delays caused by the nominated subcontractor ## Footnote None
51
What types of certificates are under JCT?
* Interim payment certificate * Practical completion certificate * Certificate of making good defects * Final Payment Certificate * Extension of time certificate * Non-completion certificate * Sectional completion certificate * Final Certificate ## Footnote None
52
What are the key responsibilities of the contract administrator (6)?
* Administering and managing the contract * Dealing with payment provisions and assessing contractor's valuation * Carrying out inspections for certification * Issuing contract instructions * Certifying sectional and/or practical completion * Agreeing the final account ## Footnote None
53
What is the role of an employer's agent?
* Acts as the employer's representative under JCT Design & Build * Issues instructions, notices, and certificates under the contract ## Footnote None
54
How does an employer's agent differ from a contract administrator?
* Contract administrator is more impartial * Employer's agent acts on behalf of the employer * Employer's agent has less impartiality compared to contract administrator ## Footnote None
55
is payment for materials stored off-site generally permitted under a JCT Contract?
generally only permitted if those materials are designated as “Listed Items” in the contract. If materials are not listed, the contractor cannot claim payment for them while they are stored off-site unless specific contractual provisions are made.
56
How to Enable Payment for Off-Site Materials
To allow payment for off-site materials safely, the contract should include: 1. Listed Items Schedule – identifying specific materials eligible for off-site payment. 2. Vesting Certificate – confirming title has passed to the Employer. 3. Insurance Evidence – showing materials are insured against loss/damage. 4. Clear Labelling and Separation – materials must be marked and stored separately. 5. Advance Payment Bond – optional, to secure Employer’s payment [2].
57
Under the JCT Standard Building Contract (SBC) 2016, the timeline for agreeing the final account after practical completion?
The Contractor must submit all documents necessary for adjusting the Contract Sum within 6 months of the Practical Completion Certificate or the last Section Completion Certificate. Once the contractor’s documents are received, the Architect/Contract Administrator must issue a Final Account Statement within 3 months If the contractor fails to submit within 6 months, the Architect/CA may issue a 1-month notice requiring submission. If the contractor still fails to respond, the Architect/CA (or Quantity Surveyor) can prepare the Final Statement based on available information The Final Certificate must be issued within 2 months of the latest of: End of the Rectification Period Issue of the Certificate of Making Good Date the Final Account Statement is sent to the contractor
58
when must the Final Certificate be issued by under JCT?
The Final Certificate must be issued within 2 months of the latest of: - End of the Rectification Period -Issue of the Certificate of Making Good -Date the Final Account Statement is sent to the contractor
59
difference between Final Account Procces under JCT SBC & JCT D&B
It is less fromal under D&B contract, with no strict timeline for final account submission. The SBC has a defined process with timelines (6 months then 3 months, followed by 2 months for the final certificate)
60
what are the payment timescales under JCT?
=7,5,5 1. The contractor is required to make an Interim Payment Application 7 days before each Interim Valuation Date/Due Date 2.Employer/ CA must issue a Payment Notice no later than 5 days after the Due Date 3. The Final Date for Payment is 14 days after the Due Date 4. If the employer wishes to issue a Pay Less Notice, they must do so no later than 5 days before the Final Date for Payment.
61
What is an EoT? how long does the CA have to make a decision?
An EOT is an adjustment of the completion date. The contractor is eligible for an EoT if a relevant event occurs. The CA must notify the contractor if their decision as soon as reasonably practicable OR within 12 weeks of receiving the notice.
62
What is a Relevant Event? Provide some examples
An event that causes a delay in the completion of the works, either caused by the employer or neither party. examples: - exceptionally adverse weather - civil commotion -variations instructed by the employer - delay in giving posession of the site -delay in receiving necessary information
63
what are the different procurement routes? Explain the differences?
-Traditional (lump sum, two-stage) - Design & Build - Construction Management (client holds contracts) - Management Contracting (MC holds contracts) - Measurement Contract - Patrtnering PPI
64
What is the aim of a procurement strategy?
to identify the best way of achieving the objectives of the client.
65
what types of insurance are typically included within a contract (7)?
Contract Works Insurance (All Risks) * Covers physical damage to the works during construction. * Includes materials, plant, and temporary works. * Can be arranged by either the contractor or employer, depending on the contract. * Often referred to as “Works Insurance”. 2. Public Liability Insurance * Covers injury or damage to third parties or their property. * Typically held by the contractor. * Required throughout the construction period. 3. Employer’s Liability Insurance * Covers injury or illness to the contractor’s employees. * Legally required under UK law. * Usually held by the contractor. 4. Professional Indemnity Insurance * Covers design-related errors or omissions. * Essential in Design and Build contracts or where consultants are involved. * Typically held by designers, architects, or contractors with design responsibility. 5. Product Liability Insurance * Covers defects in materials or products supplied. * May be required if the contractor supplies equipment or systems. 6. Existing Structures Insurance * Covers damage to existing buildings on site. * Usually arranged by the employer, especially in refurbishment projects. 7. Non-Negligence Insurance (6.5.1 Insurance) * Covers damage to adjacent properties caused by the works, not due to negligence. * Often required in urban or sensitive locations. * Typically arranged by the employer.
66
What would you expect to be included in a contract?
1. Project particulars (parties) 2. Scope of works (detailed description, reference to drawings, specifications & employer's requirements) 3. Contract particulars 4. Contract sum and payment terms (interim payments, retention, final account, valuation procedures, payment schedules) 5. Programme and completion (start and end dates, key milestones, extension of time provisions and liquidated damages for delay 6. Design responsibility 7. Instructions & variations processes 8. Quality and standards (compliance with building regulations, BS and specifications, testing, inspection and defects liability) 9. H&S (obligations under CDM regs) 10. Insurance & Bonds (public liability, employer's liability, contract works insurance, performance bonds or parent company guarantees) 11. Termination and suspension 12. Dispute resolution (often includes a notice of adjudication procedure) 13. Contract documents (forms of agreement, conditions of contract, drawings and specifications, bills of quantities or schedules of rates)
67
Difference between partial and sectional completion?
Sectional completion: - is planned and defined from the outset. Written into the contract. - Works are divided into sections with their own completion dates, LADs, possession & handover - Common in phased developments (schools, hospitals, housing schemes) Partial completion: - Not planned from the start, isn't written into the contract - Contractor offers part of the works as complete, employer agrees to take possession - No separate completion date or LADs unless agreed. - Often used when the employer wants early access to part of the site, may require agreement on adjustment of insurances, liability and access
68
What is a performance bond?
- It is an insurance policy, a requirement for the contractor to take out a bond (typically 10% of the construction value), - if the contractor defaults or goes insolvent (fails to meet their contractual obligations), the bond payer pays out to the client which is used to secure the site & stabilise the works. - Issued by a third party
69
what is a force majeure event
In a JCT contract, force majeure refers to unforeseeable events beyond the control of the parties that prevent the contractor from fulfilling their obligations — particularly completing the works on time. it is listed as a Relevant Event under which the contractor may claim an extension of time.
70
What constitutes a contract?
there are four key elements required to make a binding contract and surveyors must be aware of these: offer, acceptance, consideration, and an intent to create legal relations.
71
what are the different types of construction contract?
- JCT – Joint Contracts Tribunal – project complexity, value, sectional completion etc. - ICE – Institute of civil engineer’s – civil engineering - FIDIC- International Federation of Consulting Engineers – international parties - NEC – New Engineering Contract- promotes collaboration and project management
72
what are the differences between the different JCT contracts? How would you select one?
“ I would refer to the Guide to selecting the appropriate JCT main contract” - a standard building contract is appropriate for larger or more complex works, including specialist work or building services, that are procured by the traditional route. - Intermediate contracts are meanwhile appropriate for simpler construction projects that require all the recognised trades but no specialist works. - Minor Works contracts are for small, simple projects, that don’t require ant specialist works, nominated subcontractors or sectional completion.
73
What are the different types of tender? (5)
1. Open tendering -advertised publicly, anyone can tender 2. Selective tendering – pre-approved list of contractors invited, based on prequalification or past performance 3. Negotiated Tendering - direct negotiation, often used for specialist or complex projects 4. Two-stage tendering- early contractor involvement, price and scope negotiated during second stage 5. Framework tendering – framework agreement, efficient for repetitive works
74
key roles and responsibilities of the Contract Administrator?
- Undertaking site inspections (works progress, quality and workmanship against contract documentation), the CA needs to check work only for the purpose of certification. - Dealing with payment provisions, assessing the contractor’s sum, issuing payment certificates - Issuing contract instructions - certifying practical completion - agreeing the final account
75
what is the JCT variation procedure?
- Variations must be issued in writing by the CA. if an instruction is given orally, the contractor must confirm in writing within 7 days.
76
how should a variation be valued by the CA?
Valuing a variation is based on contract rates (if available) fair valuation of no applicable rates exist (comparison to similar projects, use of cost index information i.e. BCIS), dayworks rates for certain types of works, consideration of preliminary costs etc.
77
What should a contract instruction typically include?
A contract instruction should include: instruction number, date of issue, project details, description of instruction, location of works, reason for instruction, impact on programme & impact on cost.
78
How long does a CA have to notify the contractor of their decision in relation to an EoT?
- Under JCT contractors, the CA should notify the contractor of their decision as soon as reasonably practicable or within 12 weeks of the notice.
79
what should be included in a contractor's notice for an EoT? When should they provide this by?
- The contractor’s notice must include: the cause of the delay, whether the cause is a relevant event, an estimate of the delay to completion. - The contractor is obliged to provide a notice (in writing) ‘as and when it becomes reasonably apparent’ which tends to mean within a maximum of 5 working days.
80
Types of certificate under JCT?
1. Interim payment certificate 2. Practical completion certificate 3. Certificate of making good defects 4. Final Payment Certificate 5. Extension of time certificate 6. Non-completion certificate 7. Sectional completion certificate 8. Final Certificate
81
how does the JCT Measured Term contract work?
Key Features * Measured Work Basis: ○ Each job is priced using a schedule of rates or bills of quantities. ○ Contractor is paid for actual measured work done, not a lump sum. * Term Agreement: ○ Covers a fixed period rather than a single project. ○ Allows flexibility for multiple small works without separate contracts. * Instructions: ○ Employer issues work orders during the term. ○ Contractor executes works under agreed conditions. * Payment: ○ Based on measured quantities and agreed rates. * Risk Allocation: ○ Similar to other JCT forms but tailored for ongoing works rather than one-off projects.
82
what is the difference between a nominated and named subcontractor?
✅ Nominated Subcontractor * Selection: Chosen by the employer (client) and formally nominated to the main contractor. * Contractual Relationship: ○ The subcontractor signs a subcontract with the main contractor, but the employer influences the choice. * Implications: ○ The main contractor is responsible for managing the subcontractor’s work, but risks can be complicated because the contractor didn’t choose them. * Common Use: ○ Specialist trades or suppliers specified by the client (e.g., lifts, M&E systems). ✅ Named Subcontractor * Selection: Listed in the tender documents as preferred or recommended by the employer. * Contractual Relationship: ○ The main contractor chooses whether to use them and enters into a normal subcontract. * Implications: ○ Greater flexibility for the contractor; less employer control than nomination. * Common Use: ○ When the client wants influence but not full responsibility for selection. Key Difference * Nominated: Employer directs the choice → contractor has less say. * Named: Employer suggests → contractor decides. Recent changes in the JCT 2024 suite have significantly affected the use of named and nominated subcontractors: - The use of nominated subcontractors has been discontinued. - JCT contracts no longer include standard provisions for nomination. This reflects industry practice and risk allocation trends: contractors remain fully responsible for subcontractor performance, even if the employer influences selection.
83
what recent changes were made to the use of named and nominated subcontractors under the JCT suite of contracts?
Recent changes in the JCT 2024 suite have significantly affected the use of named and nominated subcontractors: - The use of nominated subcontractors has been discontinued. - JCT contracts no longer include standard provisions for nomination. This reflects industry practice and risk allocation trends: contractors remain fully responsible for subcontractor performance, even if the employer influences selection.
84
what is a PC (Prime Cost) sum?
A Prime Cost Sum (PC Sum) is an allowance included in a construction contract for the supply of specific items or materials, where the exact cost is not known at the time of tender. It covers the net cost of the item only, excluding installation and associated overheads. ✅ Key Characteristics Purpose: - Used for items like sanitary ware, kitchen units, or specialist fittings where the client wants flexibility in final selection. What It Includes: - The estimated cost of the item(s) supplied by a nominated supplier. What It Excludes: - Contractor’s overheads, profit, and installation costs (these are added separately). Adjustment: - If the actual cost differs from the PC Sum, the contract sum is adjusted accordingly. ✅ Difference from Provisional Sum Prime Cost Sum: For supply of goods only. Provisional Sum: For work or services where scope is uncertain.
85
What is a provisional sum and how does it differ from a PC sum?
* A provisional sum is an allowance in the contract for work that cannot be fully detailed or priced at the time of tender, because its scope is uncertain. It covers labour, materials and associated costs for the work. Actual cost is determined later when the scope becomes clear. * A Prime Cost Sum is an allowance for the supply of specific items that the client will select later. It covers material costs only, not installation. The contractor adds a fixed percentage for overheads and profit.
86
What's the difference between a defined and undefined provisional sum?
The difference between defined and undefined provisional sums relates to how much detail is provided about the work included in the allowance: * With a defined PSUM, The scope of work is described clearly enough for the contractor to understand what is involved and price related preliminaries (e.g., labour, plant, overheads). - Contractor can make reasonable allowances for time, resources, and site setup. - With an undefined PSUM, The scope of work is not described in sufficient detail, so the contractor cannot reasonably predict what is required. - Contractor cannot price preliminaries accurately; adjustments will be made later when details are known.
87
what is the difference in risk the client is exposed to with defined vs. undefined PSUMS?
* provisional sums have a lower risk level than an undefined sum. The scope was clearly described, so the contractor could allow for prelims, overheads and programming. * Undefined provisional sums have a greater exposure to cost overruns, programme delays, and claims for additional preliminaries and a Higher likelihood of disputes over what was included in the original allowance.
88
What does “time at large” mean and what is the implication when it occurs?
* It occurs when the contractual completion date becomes unenforceable because the employer (or client) has lost the right to impose liquidated damages for delay. * Essentially, the contractor is no longer bound by the original completion date and only needs to finish the works within a reasonable time. Common causes: * No valid extension of time mechanism in the contract. * Employer causes delays but fails to grant extensions. * Contract provisions for time become void (e.g., due to breach or ambiguity). Disputes often arise over what constitutes “reasonable time.”
89
What legal framework applies to construction projects for contract administration?
The legal framework for contract administration in UK construction projects is based on a combination of common law principles, statutory regulations, and standard-form contracts. Common Law : * English contract law governs how contracts are formed, interpreted, and enforced. * Key principles: offer, acceptance, consideration, and intention to create legal relations. Statutory Law: * Includes legislation such as: ○ Housing Grants, Construction and Regeneration Act 1996 (payment and adjudication rules). ○ Building Safety Act 2022 (post-Grenfell safety requirements). ○ Procurement Act 2023 (public sector procurement rules). Case Law : Judicial decisions shape interpretation of contract clauses and dispute outcomes. Surveyor's appointment is covered under separate terms of engagement/ appointment document ( professional services contract). - Also governed by English Contract Law principles.
90
what is the usual decision period for adjudication?
Decision usually within 28 days of referral (can be extended by agreement). This speed prevents delays in payment and project progress. Under the Construction Act 1996, any party to the contract has a right to refer a dispute to adjudication at any time. Process: - Notice of Adjudication served by the referring party. - Adjudicator appointed (by agreement or nominating body). - Referral document submitted with evidence. - Adjudicator reviews submissions and issues decision. Decision is temporarily binding: - Must be complied with immediately. - Can later be challenged in court or arbitration.
91
What does reasonable skills and care mean?
It is an implied duty under UK law (Supply of Goods and Services Act 1982 and common law). Requires a professional to perform their work to the "standard expected of a reasonably competent person in that profession". If a surveyor or contractor fails to meet this standard, they may be liable for professional negligence. Example: - A building surveyor must identify obvious structural defects during an inspection. - Missing a major defect that a competent surveyor would reasonably detect could breach this duty.
92
what must be established to prove professional negligence?
To prove professional negligence, the following must be established: 1. Duty of Care The professional owed a duty to the client (usually through a contract or implied by the relationship). 2. Breach of Duty - The professional did not meet the standard of reasonable skill and care expected of a competent practitioner in that field. 3. Causation - The breach directly caused the client’s loss or damage. 4. Loss - The client suffered a measurable financial or physical loss as a result.
93
What are the timescales for an extension of time under JCT?
Under JCT Contracts you’re obligated to provide notice “as and when it becomes reasonably apparent” rather than during a prescribed time frame. This is the standard drafting of the JCT and tends to mean within a maximum of five working days. Whether an extension of time is granted or not the CA must notify the contractor of their decision as soon as is reasonably practicable and within 12 weeks of receipt of the notice. * Under JCT 2024, the employer (or contract administrator) must assess and notify its decision within 8 weeks of receiving the contractor’s notice. * They can request further information within 14 days of the claim being made.
94
What is the definition of 'exceptionally adverse weather'
The term “exceptionally adverse weather” is commonly used in UK construction contracts (including JCT) but it is not precisely defined in the contract itself. Instead, its interpretation relies on industry practice and case law: * Weather conditions that are significantly worse than the norm for the location and time of year, based on historical averages. * It goes beyond ordinary seasonal variations and includes events that are rare or extreme. * Typically measured against long-term meteorological data (often 10–30 years) for the site’s region. If conditions exceed the statistical average for that period and location, they may be deemed “exceptionally adverse.”
95
what are some examples of relevant matters?
Examples of Relevant Matters (JCT Standard Building Contract clauses 4.20–4.21) 1. Failure to give possession of the site on time. 2. Architect/Contract Administrator instructions that cause disruption or additional cost (e.g., variations). 3. Suspension of work due to the employer’s default. 4. Discrepancies or divergences in contract documents that require correction. 5. Late provision of information by the employer or their team. 6. Employer’s impediment or prevention of regular progress. 7. Compliance with statutory requirements where the employer bears responsibility.
96
What does the certificate of making good trigger?
Under the JCT suite of contracts, the Certificate of Making Good Defects (issued after the contractor has rectified defects during the Rectification Period) triggers several important consequences: 1. End of Contractor’s Obligation for Defects * Confirms that all notified defects have been made good. * The contractor’s responsibility for defects under the contract effectively ends (except latent defects or those arising later under common law). 2. Release of Retention * The remaining retention (usually 50% held after Practical Completion) becomes due for payment to the contractor. * This is often the final payment under the contract. 3. Final Account Settlement * The certificate allows the Final Certificate to be issued, which concludes the contract financially. * After the Final Certificate, the employer’s ability to make further claims is severely limited (subject to contractual and statutory rights). 4. End of Rectification Period * Marks the formal close of the Rectification Period (often 6–12 months after Practical Completion). * No further scheduled inspections for defects under the contract.
97
how would a latent defect be dealt with?
A latent defect is a fault in the works that is not discoverable by reasonable inspection at the time of completion but appears later. * The contractor’s obligations under the contract usually end after the Final Certificate, so latent defects are not covered by the normal rectification process. * However, the employer can still pursue remedies under common law (breach of contract or negligence) within the statutory limitation period: * 6 years for simple contracts. * 12 years for contracts executed as a deed. Practical Steps * Investigate and document the defect. * Seek expert opinion to confirm it was due to defective design, workmanship, or materials. * Notify the contractor or designer (if still within limitation period). * Consider alternative dispute resolution before litigation.
98
what are collateral warranties?
A collateral warranty is a promise given by a contractor, subcontractor, or designer to a third party (such as a funder, tenant, or purchaser) that they will perform their duties under the main contract with reasonable skill and care. It creates a direct contractual link between the warrantor and the beneficiary.
99
what does privit of contract mean?
Privity of contract is a legal principle that means only the parties to a contract have rights and obligations under it. In other words: * If you are not a party to the contract, you cannot enforce its terms or be bound by them. * This prevents third parties from suing or being sued based on that contract. To give third parties rights, mechanisms like: * Collateral Warranties * Third Party Rights under the Contracts (Rights of Third Parties) Act 1999 are used.
100
what are third party rights?
* Third Party Rights refer to legal rights granted to someone who is not a party to the original contract, allowing them to enforce certain terms of that contract. * Normally, under privity of contract, only the contracting parties have rights and obligations. Third Party Rights overcome this by using the Contracts (Rights of Third Parties) Act 1999 or similar provisions. * Rights must be expressly stated in the contract. * Does not impose obligations on the third party—only gives them enforcement rights.
101
what is the difference between assignation and novation?
Assignation (Assignment in English law) * Definition: Transfer of rights under a contract from one party (assignor) to another (assignee). * Key Points: ○ Only rights (benefits) can be assigned, not obligations. ○ Consent of the other original party is not usually required, but notice must be given. ○ Common in construction: assigning the right to receive payment or warranties. Novation * Definition: Substitution of a new contract or party for an old one, transferring both rights and obligations. * Key Points: ○ Requires consent of all parties (original and new). ○ Creates a new contract; the old one is discharged. ○ Common in design-and-build projects when a consultant’s appointment is novated to the contractor.
102
what section if the JCT IBC covers CDP items? What does the clause specify?
In the JCT Intermediate Building Contract (ICD), the provisions for Contractor’s Design Portion (CDP) are primarily covered in: * Section 2 – Definitions and Interpretation, where CDP is defined. * Section 3 – Contractor’s obligations, which sets out the contractor’s responsibilities for design and compliance. Schedule 1 – Contractor’s Designed Portion, which details the scope, requirements, and procedures for CDP items. The CDP clauses specify: - The parts of the works the contractor must design. - Submission and approval procedures for design documents. - Liability for design and fitness for purpose. - insurance requirements for design responsibility.
103
what is the critical path?
The longest sequence of dependent tasks in a project that determines the shortest possible duration to complete the project. Why it matters: Any delay in a task on the critical path will directly delay the entire project because there is no slack (or float) in these tasks.
104
What are the relevant contract section and clauses for an EOT request?
For an Extension of Time (EOT) request under the JCT Intermediate Building Contract (IBC), the relevant sections and clauses are primarily located in Section 2 (Carrying out the Works): 1. Clause 2.19 – Notice of Delay ○ The contractor must give written notice to the Architect/Contract Administrator whenever the works are delayed or likely to be delayed. ○ The notice should state the cause of delay and any information reasonably necessary for assessment. [contract-c...ltants.com] 2. Clause 2.20 – Relevant Events ○ Lists the events that entitle the contractor to an EOT (e.g., variations, exceptionally adverse weather, force majeure, delays by statutory undertakers, employer’s instructions, failure to give possession of site). [liongate.build] 3. Clause 2.21 – Assessment of Extension ○ The Architect/Contract Administrator must assess whether completion is delayed due to a Relevant Event and grant a fair and reasonable extension of time. [contract-c...ltants.com] 4. Clause 2.22 – Further Information ○ The contractor must provide any additional details reasonably required for the assessment of EOT. [contract-c...ltants.com]
105
what are the sections and coverage of the JCT IBC (4)?
Sections and Coverage: 1. Articles of Agreement Sets out the parties, project details, contract sum, and key dates. Includes declarations about collaborative working and compliance with Building Regulations. 2. Recitals Describes the background of the contract, including design responsibility and documents forming the contract. 3.Contract Particulars Provides project-specific details such as insurance options, liquidated damages, and principal designer/contractor appointments. 4.Attestation Signature section for formal execution of the contract.
106
what are the 8 sections of conditions in the JCT IBC and what do they cover?
Conditions (Main Body) These are divided into thematic sections: Section 1 – Definitions - Defines key terms used throughout the contract. Section 2 – Carrying Out the Works - Covers obligations for workmanship, compliance, and instructions. Includes Extension of Time (EOT) provisions and Relevant Events. Section 3 – Control of the Works - Deals with possession of the site, progress, and completion. Section 4 – Payment - Sets out payment procedures, notices, and final account rules. Section 5 – Loss and Expense - Governs claims for additional costs due to delays or disruptions. Section 6 – Injury, Damage and Insurance - Details indemnity and insurance requirements. Section 7 – Termination - Specifies grounds and procedures for ending the contract. Section 8 – Dispute Resolution - Provides mechanisms for adjudication, arbitration, or litigation.
107
what are the relevant sections and clauses for a loss and expense request in the JCT IBC?
For a Loss and Expense (L&E) request under the JCT Intermediate Building Contract (IBC), the relevant sections and clauses are mainly in Section 5 – Loss and Expense of the Conditions: Clause 5.2 – Contractor’s Entitlement - States that if the regular progress of the works is materially affected by a Relevant Matter, the contractor is entitled to reimbursement of direct loss and expense incurred. [newmanor.com] Clause 5.3 – Notice of Likely Loss and Expense - The contractor must notify the Employer/Contract Administrator as soon as the effect becomes reasonably apparent, detailing: - The cause (Relevant Matter). - The likely nature and extent of the loss and expense. [contract-c...ltants.com] Clause 5.4 – Provision of Information - The contractor must provide information reasonably necessary to enable the Contract Administrator to ascertain the amount due. This includes substantiating records (e.g., time sheets, cost breakdowns). [newmanor.com] Clause 5.5 – Ongoing Updates - Requires the contractor to update the assessment and provide further details until the total amount can be determined. RELEVANT MATTERS are listed in Section 2 (Carrying out the Works) and include: Variations. Employer’s instructions. Discrepancies in contract documents. Delay in giving possession of site. Works by statutory undertakers. Other employer-related impediments.
108
what are the main contract insurance options for the works?
Option A - Contractor arranges Joint Names All Risks insurance for the works only (typically for new build). Option B - Employer arranges Joint Names All Risks insurance for the works only (new build scenario). Option C - Employer arranges Joint Names insurance for both the works and the existing structure (used for refurbishment/extension projects).
109
What information should be included in a contract instruction?
Essential Information: 1. Title and Reference - Clearly state it is a “Contract Instruction” and include a unique reference number. 2. Date of Issue - The date the instruction is given. 3. Project Details - Project name, site address, and contract reference. 4. Parties - Name of the contractor and the issuing party (Architect/Contract Administrator). 5. Description of Instruction - Detailed description of what is required (e.g., variation, design change, compliance requirement). - Include drawings, specifications, or sketches if relevant. 6. Reason for Instruction - State why the instruction is issued (e.g., design change, statutory compliance, correction of defect). 7. Timing - Indicate when the work should start and any deadlines. 8. Impact on Programme - Note if the instruction may affect the completion date or requires an Extension of Time assessment. 9. Impact on Cost - State if the instruction is a variation that may affect the contract sum (and that valuation will follow). 10. Signatory - Signature and designation of the person issuing the instruction.
110
What are the key differences between the NEC and JCT contracts?
1. Contract Philosophy - NEC: Focuses on collaboration and proactive management. It uses plain English and promotes early warning systems to manage risks. - JCT: More traditional and legalistic, with detailed clauses and a reactive approach to disputes. 2. Language and Style - NEC: Written in simple, clear language to reduce ambiguity. - JCT: Uses formal legal language, which can be harder for non-lawyers to interpret. 3. Risk Management - NEC: Encourages early warning notices and risk registers to deal with issues before they escalate. - JCT: Risks are allocated in a more traditional way, and issues are often addressed after they arise. 4. Structure - NEC: Modular system (e.g., NEC4 ECC, PSC, TSC) with options for pricing and risk allocation. - JCT: Different forms for different procurement routes (e.g., Design & Build, Standard Building Contract), but less modular. 5. Payment Mechanisms - NEC: Uses activity schedules or bill of quantities, with emphasis on regular assessments. - JCT: Typically uses interim valuations based on work done. 6. Dispute Resolution - NEC: Promotes dispute avoidance through collaboration and early warnings. - JCT: Provides traditional mechanisms like adjudication, arbitration, or litigation. 7. Flexibility - NEC: Highly flexible and adaptable for different project types. - JCT: More prescriptive and suited to conventional building projects.
111
What is the difference between the JCT & NEC contracts for PSUMS?
1. NEC Approach - NEC contracts (e.g., NEC4 ECC) use a collaborative and transparent cost management system. - They rely on Defined Cost and Schedule of Cost Components rather than provisional or prime cost sums. - If work is uncertain, it’s usually handled through compensation events or risk allowances, not PC sums. 2. JCT Approach - JCT contracts often include Prime Cost Sums and Provisional Sums for items where the exact cost or scope is unknown at tender stage. - These sums allow flexibility for later selection of suppliers or materials. 3. Why NEC avoids PC sums - NEC aims to reduce ambiguity and disputes by avoiding lump sums for undefined work. - Instead, NEC encourages early warning and agreement on changes through its change management process. - Unlike JCT, NEC does not include a specific clause for provisional sums. - NEC aims to avoid ambiguity by requiring work to be clearly defined at the outset or managed through its change control process.
112
How does NEC deal with uncertain work?
If work cannot be fully defined at tender stage, NEC uses: - Compensation Events: When scope changes or new work is instructed, the cost and time impact are assessed and agreed. - Risk Allowances: Contractors can include allowances for risks in their pricing, which are managed collaboratively. - Options for Pricing: NEC allows activity schedules, bills of quantities, or target cost arrangements to handle uncertainty.
113
what are the key differences between the 2016 & 2014 JCT contracts?
JCT 2024 modernises the suite to reflect: 1. Digitalisation (emails, e-signatures) 2. Collaboration and sustainability 3. Building Safety Act compliance 4. Clearer risk allocation and liability caps 5. New relevant events for pandemic and statutory changes 6. 2024: Adopted gender-neutral language throughout Collaborative Working: - 2016: Collaborative working was an optional supplemental provision. - 2024: Now a mandatory article (Article 3) requiring parties to act co-operatively, in good faith, and in a spirit of trust and respect. This aligns with the Construction Playbook’s emphasis on collaboration. Sustainability & Environmental Considerations: - 2016: Sustainability was an optional supplemental provision. - 2024: Incorporated into the main contract (Clause 2.1.5), encouraging contractors to propose cost-effective environmental improvements to reduce environmental impact. Building Safety Act Compliance: - 2016: No reference to new building safety regime. - 2024: Integrates dutyholder requirements for higher-risk residential buildings and clearer language around statutory compliance following the Building Safety Act 2022.
114