Under the Standard Form of Agreement, what activities are not considered standard services?
Post occupancy evaluations
Financial feasibility
What is the G series in AIA Contract Docs?
Contract Administration & Project Management forms.
What does the 1st # in the the series number determine?
Who is involved & in what capacity
What does the 2nd # in the the series number determine?
What is being covered (0= General, 5=Furniture)
A101
A152
A201
What is the B series in AIA Contract Docs?
Owner/Architect or Interior Design Services
A751
FF&E bid
A151
What is the A series in AIA Contract Docs?
Owner/Contractor Agreements or FFE Vendor
A251
A701
B153
B252
B152
What is the E Series in AIA Contract Docs?
Exhibits
What does the 3rd # in the the series number determine?
Payment/monetary responsibilities or project size
1= stipulated sum
2= Cost plus GMP
3= cost plus no GMP
4= small project
G703
Within how many days should contractor notify the owner/designer of concealed or unknown issues?
`
14 days
B253
G704
substantial completion
B254