What is the Construction Act?
Part 8 of the Local Democracy, Economic Development and Construction Act substantially amends the Construction Act. It affects all “construction contracts” in England, Wales and Scotland. The amendments to the Construction Act came into force in relation to construction contracts entered into on or after 1 October 2011 in England and Wales, and 1 November 2011 in Scotland.
The aims of the amendments are:
to increase clarity and certainty as to payment in construction contracts;
to introduce a ‘fairer’ payment regime, and improve rights for contractors to suspend their work in non-payment circumstances; and
to make adjudication more accessible for the resolution of disputes.
What are some of the common forms of contract and subcontract that are in use?
JCT (Joint Contracts Tribunal), NEC3 (New Engineering Contract), International Federation of Consulting Engineers (FIDIC), bespoke contracts are also used.
What is a “Letter of Intent”, and what information is typically included in a Letter of Intent?
What are “Third Party Rights”?
The Contracts (Rights of Third Parties) Act 1999 enables third party rights to be created by a contract. This is seen by some to offer an alternative to collateral warranties.
The overarching purpose of the act is that it allows third parties to enforce terms of contracts that they are not party to, but which benefit them in some way, or which the contract allows them to enforce.
What is are “Collateral Warranties”?
What is a contract?
Can you list 5 different bonds which might be used on a project?
What is the typical value of a performance bond?
Usually 10% of the contract sum.
What is a retention bond?
What is an advanced payment bond?
What is retention?
A percentage of the sums certified for payment under the construction contract (typically 3-5%) is held by the employer during the construction phase.
What is the purpose of retention?
It is used as an assurance of project completion and is intended as a safeguard against subsequent defects that the contractor may fail to remedy.
What are domestic subcontractors?
What are named subcontractors?
What are the advantages of naming subcontractors?
Naming a subcontractor provides the employer with more control to the selection of a subcontractor by the contractor, while still leaving them with the element of choice and the responsibility of monitoring their performance.
What are nominated subcontractors?
What are the disadvantages of nominated subcontractors?
What are the advantages of nominated subcontractors ?
On the basis the employer has nominated them in the first instance, their work should be of high quality and acceptable to the employer.
What is insolvency?
Insolvency is concerned with the inability to pay debts.
What can be done at tender stage to identify potential contractor insolvency?
What is termination?
When a contract is terminated, the parties to the contract are no longer obliged to perform their obligations under the contract.
Can the contractor suspend works for non-payment?
What are delay damages / LDs?
Key Points
What sort of expenses/costs can the employer include in the damage calculation?
This figure should not be a penalty. thus the employer needs to be realistic when identifying potential costs.