JCT 2016- Name Mechanisms to manage the life cycle of a project.
When do you issue practical completion certificate?
According to RICS guidance note “Defining completion of construction Works” 2011.
Practical Completion implications - trigger RICS Guidance Note
Practical completion - When a project is completed?
What triggers Practical completion?
Project Completion difference between NEC and JTC
Sectional completion under JTC vs Partial possession
What happens if the contractor or client disagrees with PC date?
I the contractor disagrees with the CA’s decision best course will be through adjudication.
PC - Works not in accordance with the contract and incomplete works
CA has the discretion to certify completion after consultation with the client.
Agreement between client & contractor shoudl be recorded, including additional restrictions to complete the works.
Latent and patent defects.
- latent defects cannot prevent PC
Client using works before completions. I.e moving furniture.
This can only happen with the contractor consent.
Practical completion L3. Check list.
JCT practical completion clause
15.4
Letter of intend - Types
What is a letter of intend?
Letters of intent are used in the construction industry as a way of letting procurement, site preparation or indeed construction works commence before the negotiations for the detailed construction contract have been completed.
A letter of intent is a document expressing an intention to enter into a contract at a future date but creates no contractual relationship until that future contract has been entered into. A letter of intent is not an ‘agreement to agree’.
Employers agent vs Contract administrator
Employers Agent performs the contract administration role within design and build contracts whereas the Contract Administrator performs the same contract administration role in traditional forms of contract.
Roles and responsibilities of a contract administrator.
1 BUILDING CONTRACT
JCT stands for?
Joint Contracts Tribunal
What is an EoT?
An extension of time defers the contract completion date and thereby gives the contractor a longer period within which to complete the works. In order to decide whether a contractor is entitled to an extension of time, it is necessary to establish the cause of the delay and the period of delay.
Process for claiming and EoT
Typically, the contractor has a responsibility to notify the Project Manager, when an issue might affect the project schedule. Often, a formal letter should be sent to the contract administrator outlining the request for the extension of time.
The granting of an Extension of Time relieves the contractor from liability of damages such as Liquidated Damages from the original date of contract completion for the period of the claim.
Can an EoT be claimed after PC?
JCT - yes but is not good practice
NEC s binded by time scales
What is loss and expense in a contract? JCT
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible, such as:
Under NEC contains provision for the contractor to claim payment for ‘compensation events’ rather than loss and expense.
Bingham Chapel Lane - EoT- which clause in the contract the contractor included in the letter?
JCT Design and Build Contract – Relevant Events are under Clause 2.26
Bingham Chapel Lane - Contract - Which options were discussed and that was the advise given to the client?
It was discussed:
- Traditional vs D&B
Was chose D&B for single point of responsibility. For the quality control design developed up to Stage 4
- Single stage tender to ensure best value for money