Name some standard forms of Contract
Name some JCT contract options
When would you use a Minor Works project
JCT - Name some examples of a breach of contract
JCT - what are the Relevant Events and what do they enable the Contractor
JCT - what are the Relevant Matters and what do they enable the Contractor
Enables the Contractor to an Extension of Time and Loss and Expense claim
JCT - Explain what a Performance Bond is?
Performance bond is a compensation for the Employer should the Contractor breach contract for dropping performance and duties enabling the Employer to an amount of compensation (usually 10% of contract sum) to help get another contractor appointed.
These are usually costed at 1% of 10% of the contract sum, and the contractor takes this bond out. Important standard wording is provided to the contractor to get the bond the employer wants. Two types;
- Standard ABI - has to provide relevant information to evidence the claim.
- On-Demand - doesn’t have to prove performance drop was the reason for breach and will get paid out immediately.
NEC - Name the options
Options A - G (7 different options)
A - Priced Contract with Activities Schedule
B - Priced Contract with Bill of Quantities
C - Target Contract with Activity Schedule
D - Target Contract with Bill of Quantities
E - Cost reimbursable
F - Management Contract
G - Term contract (consultant appointment)
Letter of Intent risks?
Typical order of Contract Documents?
Appendixes
A - Main Contract + Amendments
B - Employer’s Requirements
C - Contractor’s Proposals
What are Liquidated and Ascertained Damages and how are they costed?
True reflection of loss of profit from the Employer and a true reflection of consultant fees for the delay, usually per week
Under Hand vs As a deed?
Under hand - 6 years
As a deed - 12 years
This covers for breach of terms of the Contract.
As a deed includes a witness - less chance to deny doc was properly signed
How can fluctuations be managed in the JCT?
JCT provides for three approaches to fluctuations, namely
- Option A (which deals only with contribution, levy, and tax payable as an employer)
- Option B (which additionally covers labour and materials costs)
- Option C (formula adjustment using the Formula Rules).
Types of Letters of Intent?
Letter of Intent requirements?
Difference between NEC and JCT?
JCT legal written by lawyers vs NEC simple English
JCT EOT & L&E vs Compensation Events
JCT Clause in clause vs NEC no referencing within a clause
JCT Programme is not a contractual document vs NEC it is
What is a PCSA?
Pre-Construction Services Agreement (Used in Two Stage Procurement)
- PCSA allows design development
- PCSA can’t involve construction (no provision for insurance or CDM needed for site work - not demo or enabling works
- PCSA is only for one contractor therefore no commercial tension
Give some examples of Relevant Events in a JCT?
(Also relevant matters)
- Variations.
- Failure to provide information.
- Delay on the part of a nominated sub-contractor.
- Delay in giving the contractor possession of the site.
- The supply of materials and goods by the client.
Give some examples of Relevant Matters in a JCT?
Enables the Contractor to an Extension of Time and Loss and Expense claim
Latent vs Patent Defects?
Latent Defects: A latent defect is one that only an expert would be able to identify, while such a defect would not be apparent to a reasonable person upon inspection of a property. Latent defects to a property may include rising damp, faulty pool pumps or geysers, rusted internal pipes and leaking roofs.
Patent Defects: A patent defect on a property is one that should be able to be identified by a reasonable person on inspection of the property. Patent defects would include wall cracks, sagging gutters, broken windows and missing tiles.
Hudson & Emden formula?
Ways of costing Loss and Expense claim
Both pro-rata which don’t work very well, based on office overheads rather than looking at the specific project costs.
What does a Loss and Expense claim enable to the Contractor?
Extension of Time - The granting of an Extension of Time relieves the contractor from liability of damages such as liquidated damages from the original completion date for the period of the claim.
Loss and Expense
- prolongation costs
- including site as well as off-site overheads (head office costs)
disruption costs arising from a disturbance
- hindrance or interruption of a contractor’s work progress resulting in lower efficiency or lower productivity than would otherwise be achieved
- loss of profit
- finance charges
- interest.
Partial Possession vs Sectional Completion?
Partial Possession - Requires an agreement during the progress of the works. It can be more disruptive for the contractor if it is not planned well in advance.
The contractor must act reasonably and not delay in reaching his decision. He can refuse it if it will interrupt the progress of the works; make the balance of the works more expensive to complete; cause real insurance issues or pose a health and safety risk. The employer can pay these costs to obtain partial possession, but it will often be more expensive than agreeing sectional completion at the outset of a contract.
It is necessary to reach agreement on the liquidated damages to be paid by the contractor if the balance of the works are not completed on time.
Sectional Completion - Sectional Completion and the consequences are agreed up front and provided for in the contract. Once it is in the contract, the contractor has an obligation to achieve the sectional completion date. Liquidated damages are agreed up front should the section be delivered late.
What are the consequences for the client for giving PC?