What 6 conditions need to be met for a contract to be in place?
What is a contract?
A legally binding agreement (between two parties) to provide goods or services within a specified timeframe.
What are the two ways in which a contract can be executed?
What are the differences between under-hand and under-seal contracts?
Under seal:
- Requires valuable consideration (something of value)
- Executed as a deed (binding )
- Limitation period of 12 years
Under had:
- Does not require above
- Limitation period of 6 years
What is the construction act’s proper name? (HGCRA)
The Housing Grants, Construction and Regeneration Act (1996)
What does the HGCRA do?
Ensures that payments are made promptly throughout the supply chain and that disputes are resolved swiftly (provides adjudication mechanism)
Provides a framework for fairer contracts and working relationships.
What are the main suites of construction contract
Why use standard forms of contract?
Name some NEC forms of contract
What are the main types of NEC contract?
What is a target cost contract and why use it?
A ‘target cost’ is agreed between the parties which is made up of the Contractor’s estimate of the ‘Defined Costs’ plus a fee which is used is to cover the Contractor’s costs, overheads and profit.
Pros:
-beneficial where isn’t yet fully defined
- where risks anticipated are greater than usual
- motivates contractors to work in most cost-efficient way
- promotes innovation
- lump sum contract can often be overinflated to account for risk
Cons:
- contractor may use cheaper products of a lesser quality
- Differences may occur between the contractor and the client if changes occur during the project due to which cost may increase.
- Requires a lot of commercial support and auditing to maintain the contract
Why use an Option E contract?
For emergency works – cost isn’t a priority and client carries all financial risk
What is the build of the NEC contract?
What are defined costs in the NEC?
Essentially, Defined Cost = payments due to subcontractors + the cost of components for other works (such as plant, equipment, people etc.) - disallowed cost.
What are disallowed costs in the NEC?
Cost the Contractor may have incurred and fall within the definition of Defined Cost, but which the PM decides:
Disallowed Costs are therefore cost borne entirely by the Contractor
What is the NEC payment process?
Contractor submits AFP before due date > PM has 7 days to assess from due date > payment must be made within three weeks of due date.
Monthly assessment date - Amount due = Price for Work Done to Date - less retention
What is the schedule of cost components (SCC)?
It is NOT a list of rates or prices.
It just sets out what the contractor will be paid for and how that is calculated. And nearly all the items in the schedule of cost components are paid for at what they have actually cost the contractor.
What are the categories in the SCC / SSCC?
Name some common examples of Z clauses
What is the difference between ‘Plant and Materials’ and ‘Equipment’ under the NEC?
How are ambiguities dealt with under the NEC?
Clause 17 - The PM shall issue an instruction resolving the matter.
What updates have occurred between the NEC3 and NEC4?
Worth mentioning:
* Improved clarity across suite
* Payments – Contractors must submit AFPs. NEC3 = PM obliged to assess if they don’t
* Default periods for EW meetings
* Programme – ‘treated acceptance’ when PM doesn’t respond to C’s submission
* Requirement for Contractor to operate a quality management system
* Introduction of W3 option (dispute avoidance board)
General:
* Terminology
– W.I becomes Scope
– Employer becomes Client
– Risk Register becomes Early Warning Register
– PCG becomes ultimate holding guarantee (X4)
* Gender neutral
Name some differences between the NEC and JCT
What is the difference between a relevant matter and a relevant event?