What is a Target Cost contract?
Target cost is set, risk is shared and the savings/overspend are shared between the Parties at the allocated share percentages.
How does Sectional Completion work in terms of defects?
Defects Date only begins upon Completion of the whole works
How does notifying defects differ before and after Completion?
Clause 44 of the Contract:
- Before Completion – only to correct any Defects which would prevent the Client from using the works (and any other reason stated)
- After Completion - Defects must be corrected by the end of the defect correction period