What are the main parts of the NEC contract?
For NEC ECC there are 9 core clauses + Option W1/W2/W3 + contract data part 1 and part 2 + Schedule of Cost Component/ Short Schedule of cost component (dependent on which main option chosen), Y clauses, X clauses and Z clauses.
There are 6 options:
Option A priced contract with activity schedule
Option B Priced contract with bill of quantities
Option C Target contract with activity schedule
Option D Target contract with bill of quantities
Option E Cost Reimbursable contract
Option F Management contract
What are the 9 core clauses on the NEC ECC?
What are the main parts of the JCT contracts?
Name the 9 sections of the conditions in a JCT Contract
(9 sections of the conditions in a JCT contract)
1. Definition and Interpretation
2. Carrying out the works
3. Control of the works
4. Payment
5. Variations
6. Injury, damage and insurance
7. Assignment, Third Part Rights and Collateral Warranties
8. Termination
9. Settlement of disputes
What experience do you have with the NEC contract?
I have completed a contractor’s application and completed assessment of compensation events. I have also under NEC PSC provided fees and activities for CEs.
How is a contract under hand different from a deed?
Execution: A contract under hand is typically signed by the parties involved and may require witnesses, while a deed must be signed, witnessed, and delivered with the intention of it being immediately binding.
Consideration: A contract under hand requires consideration (something of value exchanged), but a deed does not require consideration to be enforceable.
Formality: Deeds generally require more formalities, such as being written on parchment, and must clearly state that they are intended to be a deed.
Limitation Period: The time limit for bringing a claim under a contract under hand is usually 6 years, whereas for a deed, it is 12 years.
In essence, deeds are more formal and have a longer limitation period for enforcement than contracts under hand. They are often used for significant transactions where no consideration is passed or where a longer enforcement period is desired.
What is Execution as a deed?
Execution as a Deed – is when the contract must be in writing and clear that the contract is a deed. Liability period is 12 years and signatory is:
* signature of director and company secretary or two directors.
* Affixing the company’s common seal in the presence of a director and company secretary or 2 directors.
* Signature of a single director in the presence of a witness who attests the signature.
What is Execution Under Hand
Can come into effect orally and no requirements to sign (however it is good practice to execute and signify acceptance to prevent future disagreement).
Liability period is 6 years
Signatory is: Single Director in the presence of a witness who attests (confirms) the signature.
What is a contract?
A legally binding document (between two parties) to provide goods and services with a specified timeframe.
What happens when ‘time is at large’?
‘Time is at large’ – Main Contractor has not fulfilled their obligation to make PC however a certificate of non-completion has not been issued. This means there is no set completion date. The Contractor’s only obligation to complete the works in a ‘reasonable time’. LDs cannot be claimed as there is no date to take them from. The employer in this event would have to try and prove that the contractor has not completed in a reasonable time.
How do you form a contract?
OACIC
Offer
Acceptance (or counter-offer)
Consideration
Intention (to create a legal relations)
Capacity (to make agreement).
What are Compensation Events?
Compensation events are similar to relevant events and matters, they entitle a contractor to claim both additional time and additional costs in relation to the completion of the works. Both PM and Contractor can notify of a CE. PM gives an instruction that will change the scope pf works and then notifies the Contractor of the Compensation event.
Why might you advise the client on a standard contract form (ie vs amended form or bespoke)
Why might you advise client to use a JCT SBC?
Standardised for ease/familiar to the project team
Designed for use when traditional procurement has been chosen.
Intended for larger projects where detailed contract provisions are necessary.
Why might you advise client to use JCT D&B?
For D&B procurement route
Earlier time on site - design and programme overlap.
Price Certainty - earlier price certainty
Risk - single point of responsibility
What are key differences between JCT and NEC?
What benefits does JCT D&B offer the client?
Designed for use when D&B procurement route has been chosen
D&B projects can vary in scale but generally suitable where detailed provisions are needed.
What Risks does the employer undertake for JCT D&B?
Risk – Employers risk pre-contract – planning permission and surveys and investigations.
Employers risk post -contract – relevant events and relevant matters
Contractors risk post contract – event that is reasonably foreseeable.
What are relevant events?
Relevant Events are events that entitle the contractor to EOT when using JCT. They are caused by the client or a neutral event not caused by any party. The contract should set out what constitutes a relevant event in 2.26:
Can you provide an example of a Relevant event?
The JCT contract should set out what constitutes a relevant event in 2.29.
Variations, Exceptionally adverse weather, Civil commotion or terrorism. Failure to provide information. Delay on the part of a nominated sub-contractor. Statutory undertaker’s work. Delay in giving the contractor possession of the site. Force majeure (such as a war or an epidemic). Loss from a specified peril such as a flood The supply of materials and goods by the client. National strikes.
Changes in statutory requirements. Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
What are relevant matters?
Relevant Matters are matter for which the client is responsible for affecting the progress of the works.
This may enable the contractor to claim direct loss and/or expense that has been incurred.
They are outlined in 4.22 of the JCT contract.
Can you provide an example of a Relevant Matters?
What is a Parent Company Guarantee?
Parent Company Guarantee is an arrangement where the contractual performance of one company in a corporate group is underwritten by the other members of the corporate group. This means that is must complete the works itself if it can or pay the financial equivalent.
What is the most common type (most common parent company guarantee) in the construction industry?
A performance bond.