What is a contract?
It is a legally binding promise (written or oral), by one party to fulfil an obligation to another party in return for consideration.
What is the difference between an implied and express term?
What is quantum meruit?
This is where a reasonable sum is paid for the services rendered or work undertaken if the amount due is not stipulated in the contract.
What does a typical pack of contract documents contain?
What legislation are you aware of that govern construction contracts in the UK?
What laws does the construction industry operate under in the UK?
Explain some of the sanctions the HGCRA 1996 imposes on construction contracts in the UK?
Explain some of the sanctions the LDEDC 2009 imposes on construction contracts in the UK?
Explain the understanding of the Unfair Contracts Act 1977 (UCTA)?
It regulates contracts by limiting the extent to which one party can avoid liability through the use of exclusion clauses.
For example: if one party was to raise prices without considering the rights of another would be considered unfair e.g. a utility provider increasing their prices without notifying the consumer or a landlord increasing rent without given sufficient notice to their tenants.
Name some families of contracts?
What are the key changes of the new JCT suite of contracts 2024?
Name some of the standard forms of JCT contract?
Name some of the conditions of the SBC/Q?
Name some of the conditions of the SBC/XQ?
Name some of the conditions of the SBC/AQ?
When is it most ideal to use the JCT SBC form of contracts?
Ideal for project with the following:
- Value in excess of £1m+.
- Programme duration of 12 months or more.
- For large complex projects.
- Administered by the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an SBC, the QS is appointed and named.
What is the JCT intermediate building contract, it’s conditions and when it’s most suitable for?
The IBC is a contract that is more detailed than the minor works building contract but not as extensive as the standard building contract. Is usually administered on projects that are procured via the traditional method and call also contain elements of CDP.
It is best suited for projects with the following conditions:
- Procured via the traditional route.
- Design is complete prior to tender.
- Can include elements of CDP, if so, then IBC with CDP must be issued.
- Is a lump sum contract.
Ideal for projects with the following:
- Value in between £250k - £1m.
- Programme duration of up to 12 months.
- For moderate sized projects although some complex areas can be included through CDP.
- Administered by the the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an IBC, the QS is appointed and named.
What is the JCT minor works building contract, it’s conditions and when it’s most suitable for?
The MW is a contract that refers to small, relatively straight forward construction projects that are less than £250k in value. Is usually administered on projects that are procured via the traditional method.
It is best suited for projects with the following conditions:
- Procured via the traditional route.
- Design is complete prior to tender.
- Can include elements of CDP, if so, then MWBC with CD must be issued.
- Is a lump sum contract with periodic payments.
Ideal for projects with the following:
- Value up to £250k.
- Programme duration of up to 12 months.
- Administered by the the contract administrator (CA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an MW, the QS is not appointed and named.
What is the JCT Design and Build (D&B) contract, it’s conditions and when it’s most suitable for?
The D&B is a contract where there is a need for a single point of responsibility for delivering the entire project. Is usually administered on projects that are procured via the design and building method.
It is best suited for projects with the following conditions:
- Procured via the D&B route.
- Design can overlap during the tender/construction and thus a programme saving can be offered.
- Is a lump sum contract with periodic payments.
Ideal for projects with the following:
- Value in excess of £500k+.
- Programme duration of 12 months or more.
- Contractor’s proposals form the basis of the contract.
- Enhances collaborative working, sustainability, 3rd party rights, bonds, collateral warranties and etc.
- Administered by the Employer’s Agent (EA), who can be either:
- Architect
- Project Manager
- Building Surveyor
- Engineer
- Quantity Surveyor
Also, under an D&B, the QS is not appointed and named.
Name some of the elements of a JCT contract?
What are some of the differences between the JCT and NEC forms of contract?
What are the differences of an EA and CA?
EA:
- Appointed and named under D&B Contracts.
- Issuing instructions for variations.
- Co-ordinating the review of information prepared by the contractor.
- Considering items submitted by the contractor for approval.
- Managing change control procedures.
- Reviewing progress of the works and preparing reports for the client.
- Validating and certifying payments.
- Considering claims.
- Monitoring commissioning and inspections.
- Arranging handover.
- Certifying PC.
- Highlighting defects to the contractor.
- Issuing certificate of making good defects.
- Agreeing the final account.
CA:
- Appointed and named under SBC, IBC and MW Contracts.
- Issuing instructions for variations.
- Administering change control procedures.
- Preparing and issuing progress reports.
- Issuing interim certificates.
- Considering claims.
- Agreeing commissioning and testing procedures.
- Issuing certificates for PC.
- Collating and issuing of schedules of defects.
- Issuing certificate of making good defects.
- Issuing final certificate.
- Chairing progress meetings.
- Co-ordinating and instructing site inspectors.
How do you go about calculating LAD’s on a project?
What are LAD’s and what needs to be in place for this to be deducted?