What does CDM stand for?
Construction Design Management
What is a QS defined as under CDM Regulations?
A designer
What is a Parent Company Guarantee?
A PCG is a guarantee given by one contracting party’s ultimate or intermediate holding company in favour of the other contracting party to secure and underwrite the performance of that party’s obligations under the contract.
What are the 5 types of bond?
Performance bond
Retention bond
Off-site materials bond
Advance payment bond
Tender bond
What is a performance bond?
A performance bond is a form of security provided by a contractor to a developer or employer.
It consists of an undertaking by a bank or insurance company to make a payment to the employer in circumstances where the contractor has defaulted under the contract.
What bond type would you recommend to your client?
PCG if available
Why would you recommend a PCG?
A performance bond is a finite sum of money where the damages claimed may be higher than the sum. A PCG is not limited.
What are Third Party Rights?
The third Party rights act 1999
The act allows third parties to enforce terms of contracts that they are not party to, but which benefits them in some way, or which the contract allows them to enforce.
What is a collateral warranty?
Forms a contractual link between two parites where one would no usually be present.
When is a collateral warranty used?
Employer —> Main Contractor –> sub-contractor
^
—
> Sub-contractor
What is the difference in co-operation principles between the two? (JCT & NEC)
NEC is considered a more collaborative approach to working. Parties are required to work in the spirit of “mutual trust and co-operation”
What happens if you don’t issue a completion/non-completion certificate?
Time is at large – LDs are unenforceable.
What is required to issue a completion certificate?
What is the process for issuing a non-completion certificate?
What is time at large?
The need for comprehensive EOT provisions in construction contracts was illustrated by early case law, e.g. Holme v Guppy (1838) – ‘an act of prevention’ (handing over the site late) in the absence of an EOT clause, results in time becoming ‘at large’. With time at large, the liquidated damages provisions are unenforceable.
What is meant by the term “Prevention Principle”
Prevention Principle – one party may not enforce a contractual obligation against the other party where it has prevented the other party from performing that obligation. If a contract contains a specified completion date but no EoT provisions, the prevention principle prevents the Employer from enforcing the date for completion where it has caused the delay (e.g. issuing an instruction). If this occurs, time becomes at large; and the original completion date falls away, and any LADs regime falls away and the contractor will only be obliged to complete within a ‘reasonable time’.
What happens once PC is achieved?
Half of retention is released
12-month defects period starts
Client needs to start insuring and securing the building
The ability to deduct LDs is ceased
What is required for Final account?
Certificate of Making Good defects
Certificate of Practical Completion
Final account Statement
How was this contract executed?
As a deed
In what capacity did you issue the Practical Completion Certificate?
Which contract, were you CA? Engineer?
As contract administrator on a minor works contract
What is the contractor required to do to achieve Practical Completion?
Works are to be substantially completed so that the building can be put to its intended use with safety and convenience.
What is Assignment?
Transferring
What if the client tells you the LADs are you be £100,000 per week?
What are extensions of time?
Extensions of time adjust the completion date and relieves the contractors liability to pay liquidated damages for the period of the extension.