What’s the difference between CA and EA?
EA = D&B
CA = SBC
What is 6.5.1. insurance?
Refers to clause 6.5.1. in JCT contract.
A requirement on the contractor to organise insurance both for themselves and the client.
This insurance provides cover should there be damage to a neighbouring property due to the works that are carried out, and the cause of which is not the result of negligence.
What does JCT DB say about retention?
3% if not stated.
What does JCT IC say about retention?
5% if not stated (95% valued)
2.5% after PC (97.5% valued)
What else did you learn about in Principles of Contract Law?
Examples of the principles, such as:
Acceptance = must be unambiguous, written or oral
Capacity = must be over 18 OR must have ability to carry out works
What is a contract?
A legally binding agreement that recognises and governs the rights and duties of the parties to the agreement
What’s a bilateral agreement?
a set of promises that each party has made to the other
What’s a unilateral agreement?
only one party will make a promise to do something if the other party actually does something stipulated by the former
What are the 6 principles of contract law?
What is NEC3 for?
Used for the appointment of a contractor for engineering and construction work, including any level of design responsibility.
It is a suite of construction contracts intended to promote partnering and collaboration.
What are the options under NEC?
I have never used NEC however know the options are:
Option A: Priced contract with activity schedule.
Option B: Priced contract with bill of quantities.
Option C: Target contract with activity schedule.
Option D: Target contract with bill of quantities.
Option E: Cost reimbursable contract.
Option F: Management contract.
Option G: Term contract (
What are the contract documents required under NEC?
What are the core clauses under NEC?
What are Z clauses?
Used to amend standard form NEC contracts. They can be inserted into NEC contracts as a means of adding conditions or amending wording.
Are you aware of any other forms of contract aside from JCT/NEC?
What are the different FIDIC contract suites?
What are the differences between JCT DB 2011 and 2016 in terms of payment?
What are the differences between JCT DB 2011 and 2016 in terms of insurances?
Under Option C the Employer maintains insurance of the existing structures and contents. Where the Employer is a tenant, home owner or other domestic employer, it is often difficult for the Employer to take out the required insurance. JCT 2016 deals with this by allowing the parties to agree to alternative insurance arrangements.
Are there any other differences between JCT DB 2011 and 2016?
JCT standard forms include provisions for performance bonds and parent company guarantees
JCT 2016 provide a time limited procedure for the prompt assessment of any loss and expense applications by the Contractor. The architect/contract administrator must now assess the claim within 28 days of receipt (14 days from any update). Under JCT 2011 there was no such time limit.
What’s the difference between a Contractr Administrator and Employer’s Agent?
CA = SBC
EA = DB
What’s the difference between the payment timeline in JCT DB 2011 and JCT IC/SB 2011?
SB/IC has Contractor’s Interim Application for Payment date
DB = Interim Application can be submitted as late as the due date
What guidance note does RICS public on payment timelines?
RICS Interim Valuations and Payments 2015
What is the payment cycle in JCT DB 2011?
14 days
What is the payment cycle in JCT DB 2016 or SBC?
21 days