Contract: Unit 5 + 6 Flashcards

(37 cards)

1
Q

Which ONE of the following is CORRECT?

S.13 of the Supply of Goods and Services Act 1982 is a condition

S.13 of the Supply of Goods and Services Act 1982 is an innominate term

S.13 of the Supply of Goods and Services Act 1982 is a warranty

A

The answer is B – s.13 of the Supply of Goods and Services Act 1982 is an innominate term.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which ONE of the following is CORRECT?

If a condition is broken, the innocent party may be able to terminate the contract as well as sue for damages

If a warranty is broken, the innocent party may be able to terminate the contract as well as sue for damages

If a condition is broken and the innocent party terminates the contract, he cannot also sue for damages

If an innominate term is broken, the innocent party can sue for damages but cannot terminate the contract

A

the only correct statement is A.

B is not correct because if a warranty is broken the innocent party can sue for damages but cannot terminate the contract.

D is not correct because if an innominate term is broken the innocent party can terminate the contract if the effects of the breach are major.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Delia owns a restaurant. She enters into a contract with the celebrity chef Nigel Bites to work at her restaurant for the months of June and July. Nigel agrees not to work as a chef elsewhere during this period. On 1 May Nigel telephones Delia and says he will not be working for her as he has received a more lucrative offer to work as a chef elsewhere.

Indicate whether the following statement is TRUE or FALSE.

Delia could obtain a decree of specific performance to compel Nigel to work for her during June and July.

A

The statement is false. The court will not order specific performance of an employment contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sportsgoods Ltd contracted to sell a consignment of tracksuits to Barnes plc for £10,000, payment to be within 10 days of delivery. Sportsgoods delivered the tracksuits a month ago. Barnes plc have not paid.

What is the most appropriate remedy for Sportsgoods Ltd?

Specific performance

Injunction

Damages

Action for the agreed sum.

A

the most appropriate remedy is an action for the agreed sum. Although Sportsgoods could sue for damages, it seems that their only loss is the amount that Barnes owes them and so an action for the agreed sum would be the best approach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tom employs Karen to paint his kitchen for £400, payment to be on completion. Karen starts work but then Tom tells her to stop as he has changed his mind.

Which ONE of the following statements is CORRECT?

Karen could sue Tom for the agreed sum of £400 because Tom wrongfully prevented her from completing the work.

Karen could obtain a decree of specific performance to force Tom to allow her to finish the work

Karen could sue for damages or for a quantum meruit

Karen’s only claim is for damages for loss of profit

A

the correct answer is C. A is not correct as the duty to pay has not yet arisen ( payment was to be on completion).B is not correct as the court will not grant specific performance of a contract for services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In April, Skytours Ltd agreed to employ Sue as a courier for 3 months starting on 1 June. In May Skytours told Sue that there had been a change of plan and her services would not be required.

Which ONE of the following is CORRECT?

Skytours is in breach of contract, but Sue must wait until 1 June before taking proceedings.

Skytours is in breach and Sue can terminate the contract and sue for damages immediately if she wishes.

Skytours cannot be in breach until 1 June as they may decide they need Sue as a courier after all.

A

B is the correct answer. Skytours have committed an anticipatory breach. This means that Sue can terminate immediately and sue for damages - she does not have to wait until 1 June.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Andrew engaged Sparrow Ltd, a firm of building contractors to repair a garden wall for £1,000 which he paid in advance. Sparrow Ltd was due to start work on 1 May. On 2 April Sparrow Ltd told Andrew that they would be unable to do the work. Andrew telephoned a few other contractors and found a firm who would repair the wall for £700 and start work on the 1 May.

What is the most appropriate remedy for Andrew?

Specific performance

Damages

Restitution - total failure of consideration

Restitution - quantum meruit

A

the most appropriate remedy would be restitution on the basis of total failure of the consideration ie Andrew would get back his £1,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Delia owns a restaurant. She enters into a contract with the celebrity chef Nigel Bites to work at her restaurant for the month of June. Nigel agrees not to work as a chef elsewhere during this period. On 1 May Nigel telephones Delia and says he will not be working for her as he has received a more lucrative offer to work as a chef elsewhere.

Indicate whether the following statement is TRUE or FALSE.

Delia could probably obtain an injunction to prevent Nigel working as a chef elsewhere during the month of June.

A

The statement is true. Injunctions have been awarded to enforce negative covenants in employment contracts and as the time limit is relatively short (1 month), and he is only prevented from working as a chef, the court would probably award an injunction in this case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Stan agrees to build a conservatory for Jade, price £12,000, payable on completion. Stan does some of the work and then abandons the job. Jade gets another contractor to finish the work for £5,000.

Which ONE of the following is CORRECT?

Stan is entitled to some payment as he has substantially performed his obligations.

Stan is not entitled to any payment for the work done.

Stan is entitled to a reasonable sum for the work he has done as Jade has accepted his partial performance.

Stan is entitled to some payment for the work he has done, but the maximum amount he can receive is £7,000.

A

B is the right answer. The doctrine of complete performance applies here – Stan has not performed his side of the contract properly and so is not entitled to payment. None of the exceptions apply here. Substantial performance does not apply as Stan has not finished the work. Jade has not voluntarily accepted Stan’s partial performance. Jade has not wrongfully prevented Stan performing the contract and the obligations are not divisible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which ONE of the following statements is WRONG?

Breach of an innominate term will only entitle the innocent party to terminate the contract if the breach had substantially deprived them of the whole benefit thye expected to receive under the contract.

If an innocent party wrongly treats breach of an innominate term as repudiatory, the innocent party may be sued for breach of contract.

Where there is an anticipatory/repudiatory breach of an innominate term the innocent party must make an immediate decision whether to affirm the contract or to accept the breach as a present breach and terminate the contract.

Following a breach of contract the innocent party must take reasonable steps to mitigate their loss: the burden of proof is on the defendant to show failure to mitigate.

A

In Gibbs v Leeds United Football Club, did Gibbs have to make a snap decision whether, or not, to resign? No, he had a reasonable time to decide and so Statement C is WRONG.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A builder made a contract with a client to refurbish the client’s offices at a total cost of £10,000 to be paid on completion. The builder abandoned the job half way through the work. None of the work has been completed to the client’s satisfaction. The client has found another builder to complete the work at a total cost of £8,000.

What damages can the client recover from the original builder?

None, as the new builder is able to complete the work at a lower cost and the client is not obliged to pay anything for the work done.

£8,000 damages, because this is the sum the new builder is charging.

£10,000 damages, because this is the sum the first builder was charging.

£2,000 damages, because the client is obliged to pay the first builder half of the cost that the new builder is charging (£4,000) as the first builder had done half the work. The total cost would therefore be £12,000 being £2,000 more than the original price.

£5,000 damages, because the client is obliged to pay the first builder half of the cost agreed under the first contract (£5,000) as the first builder had done half the work. The total cost would therefore be £13,000 being £5,000 more than the new price.

A

Option A is correct. Damages are to put the injured party – the client – in the position as if the contract had been properly performed. Importantly damages can only be recovered if the injured party has suffered a loss. £8,000 (the sum the client will now have to pay) is lower than £10,000 (the sum the client would have had to pay had the original contract been properly performed). There is therefore no loss.

It should be noted that the original contract price of £10,000 was to be paid on completion and has not been paid. The client is released from any obligation to pay this when the first builder abandoned the job.

Options B and C are wrong as neither of these properly set out the loss suffered. Damages in this case would be calculated by reference to any amount that the client had to pay in excess of the original £10,000 contract price.

Options D and E are wrong in that the client does not have to pay the first builder anything. The first builder has abandoned the job without completing any part of it. The client has no choice but to accept the work done. This is a repudiatory breach by the builder. The client can terminate the contract, i.e. is released from any further obligation to pay the sum due on completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A landlord, wanted to upgrade one of his rental properties. He entered into a contract with a bathroom fitter to remove the old bathroom fittings and to replace them with new sanitary ware. The contract price was £8,000. The landlord paid the builder £500 in advance and agreed to pay the balance on completion. The work was finished but the shower tray leaks (as it was not sealed properly) and so the shower cannot be used. The landlord is refusing to pay the balance of the contract price.

If the builder sued for breach of contract which of the following would be the most likely legal outcome?

The builder would be awarded £7,500 .

The builder would keep £500 but not be entitled to any more money.

The builder would be awarded £7,500 less the cost of properly sealing the shower tray.

The builder would have to forfeit £500 and not be entitled to any more money.

The builder would be awarded a reasonable sum in restitution for the work he had done.

A

C is correct. There has been substantial performance as the work had been finished but appears to be only slightly defective.

The builder is not entitled to £7,500 as the work was not precise/exact (the doctrine of complete performance) and so A is wrong.

B is wrong. The builder would be entitled to keep £500 in restitution (as there’s not been a total failure of consideration) but would be entitled to more money due to having substantially performed the contract

D is wrong. The builder can keep £500 advance payment in restitution as there was not a total failure of consideration.

E is wrong –the builder is not entitled to a reasonable sum for what he did as there was no voluntary acceptance of part performance (Sumpter v Hedges).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A company has agreed to build a large greenhouse in a woman’s garden with a south-facing entrance. The total cost was £4,000, payment on completion. After the greenhouse has been built, the woman discovered that the door is facing north and the roof is not waterproof. It will cost £3,500 to put things right. The woman refuses to pay the company.

Which of the following best describes if the company is entitled to some payment?

The company is entitled to full payment as the greenhouse has been built.

The company is not entitled to full payment but they are entitled to some payment as the greenhouse has been built by them.

The company is not entitled to some payment as the work is seriously defective.

The company is entitled to full payment minus the cost of putting things right because it has substantially performed its obligations.

The company is entitled to some payment minus the cost of putting things right because it has substantially performed its obligations.

A

Option C is correct. The work completed by the company is seriously defective and it will cost £3,500 to put it right compared to a contract price of £4,000. As a result, the contractor is not entitled to any money.

Options A and B therefore are wrong.

Options D and E are wrong. For substantial performance to apply the work has to be finished and only be slightly defective, which is not the case here on the facts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A builder and a man enter into a contract for the builder to construct a garage for the man. The agreed price is £10,000 (being £1,000 to clear the site, £5,000 for building materials and £4,000 for labour) payable on completion of the work. The builder begins work by clearing the site. Before the builder commences construction of the garage they realise they have not charged enough for the work and will not be able to finish the job and make a profit. The builder asks the man for more money but the man refuses. The builder decides to abandon the job.

The builder sends an invoice to the man for £500 to cover the cost of clearing the site. The man refuses to pay the invoiced sum.

The man employs a new builder who completes the garage at an agreed price of £9,750. The builder commences legal action to claim the sum due under the invoice.

Will the man be liable to pay the £500?

Yes, because in providing their services the builder provided good consideration for the sum claimed under the invoice.

Yes, because the builder had finished the first stage of the job and is entitled to be paid for this work.

No, because the man will be entitled to damages due to the builder’s breach of contract and the man’s damages will exceed the invoiced sum.

Yes, because the man voluntarily accepted the work done to clear the site.

No, because the builder would only be entitled to payment when they complete the work.

A

Option E is correct. The man promised to pay £10,000 on completion of the work. In a contract where the parties agree that the work must be done before the price falls due, the doctrine of complete performance provides that the builder will only be entitled to the price when performance is complete. As the builder did not complete the work then they are not entitled to any part of the contract price.

Options A and B are wrong because the man did not promise to pay £500 for the clearance of the site. He agreed to pay the full price when the job was complete.

The builder is in breach of contract but the man does not appear to have suffered any loss. He has paid £9,750 for his new garage. This is less than the sum he agreed to pay the builder. As the man has suffered no loss, Option C is wrong.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A contractor agreed to design, craft and fit a new oak staircase in a client’s entrance hall for an agreed price of £14,000. The client paid the contractor £4,000 when the job was agreed, with the balance to be paid once the staircase was fitted.

The contractor completed the work but the client is unhappy with the staircase and is refusing to pay the contractor the balance of the price. The client has complained that whilst the oak and glass banister and the stair treads are excellent, the skirting along the walls is shoddy and the under stair panels do not fit flush with the banister, showing daylight between the joints. The client has had a quote of £1,500 to rectify these imperfections.

Which of the following statements provides the best advice for the client about the balance of the price?

The contractor will not be entitled to the balance of the price as the contractor has not performed the contract precisely and exactly.

The contractor will not be entitled to the full balance of the price, but will be entitled to the balance less the cost of putting right the defects.

The contractor will not be entitled to the full balance of the price, but will be entitled to either damages or a reasonable sum in restitution for what the contractor has done.

The contractor will be entitled to the full balance of the price as the contractor has substantially performed the contract.

The contractor will be entitled to the full balance of the price as the contractor has performed their obligations under the contract.

A

Option A is the best option as the doctrine of complete performance will apply. It is unlikely the contractor would be able to establish they have substantially performed the contract and that the work is only slightly defective, as the cost of rectifying the problem is more than 1/14th the contract price. As a result, options B and D are unlikely to be the best advice.

Option C is wrong as these remedies are usually applicable when a contracting party has been wrongly prevented from performing contractual obligations, and in this case the contractor has not been prevented from completing the contract.

Option E is wrong because the work is defective so the contractor has not completed the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A client, a professional singer, signed a one-year contract with a record producing company (the ‘Company’) under which the client agreed not to work for any other record company during that time. However, the client has signed a contract with another company in breach of the restriction and the Company is seeking an injunction.

Which of the following statements best describes whether, or not, the Company’s action will succeed?

No: an injunction will not be ordered because it would have the effect of forcing the client to work for the Company.

No: damages would be adequate and it would be inequitable to grant an injunction.

No, because to order an injunction would be contrary to public policy as an undue restraint on earning a living.

Yes, because an injunction would not prevent the client from earning a living in any capacity other than as a singer.

Yes: as damages would be inadequate an injunction would be granted as of right to the Company.

A

Statement D is correct- Warner Bros Pictures v Nelson.

Statements A and C are wrong because an injunction would not stop the client earning a living in any capacity other than as a singer. The client could still work for example in retail.

Statement B is wrong as damages would not be adequate.

Statement E is wrong as injunctions are not granted as of right. They are a discretionary remedy.

17
Q

A client contracted to sell a consignment of tracksuits for £10,000, payment to be within 10 days of delivery. The signed contract included the following term ‘Time for payment shall be of the essence’ ie a condition of the contract. The client delivered the tracksuits a month ago but has still not been paid for them.

What is the MOST APPROPRIATE remedy for the client?

Specific performance

Injunction

Damages

Action for the agreed sum

Termination

A

Statement D is correct. As a fixed amount of money is being claimed action for an agreed sum (ie the money owed) is the most appropriate remedy. Action for an agreed sum is a debt action.

A and B are wrong as monetary compensation will be adequate.

C is wrong. Damages are subject to limitations such as remoteness and mitigation. When a fixed sum is owed and claimed there are no such issues.

E is wrong because although ‘Time for payment shall be of the essence’ means it is a condition of the contract it would be too late for our client to terminate. The goods have been delivered and so there is no future performance to terminate.

18
Q

A company (‘the Retailer’) entered into a contract with another company (‘the Supplier’) to buy 30,000 flat-pack boxes at a price of £60,000. The Retailer paid £20,000 in advance. When delivered the boxes were defective and the Supplier was unable to supply replacement boxes. The Retailer rejected the boxes and did not pay the balance of the purchase price. To avoid incurring further losses, the Retailer obtained replacement boxes from another supplier for £70,000.

Ignoring interest, what sum can the Retailer properly claim against the Supplier?

£70,000

£10,000

£30,000

£20,000

£60,000

A

C is correct. The retailer paid £20,000 in advance to the supplier. The supplier gave nothing in return for that – there was a total failure of consideration and so the retailer is entitled to be reimbursed £20,000 in restitution. In addition it has cost the retailer an extra £10,000 to buy similar goods elsewhere and so the retailer would be able to claim that sum as loss of expectation damages. The retailer took reasonable steps to mitigate its loss.

A and E are wrong as the retailer would have made a windfall profit as a result of the breach.

B is wrong because it does not take account of £20,000 paid in advance for which the retailer received nothing in return.

D is wrong as it ignores the extra money the retailer had to pay to buy replacement goods elsewhere.

19
Q

A client company (the Client) entered into a written contract with another company (the Company) which was drafted by a director of the Company. One particular term of the contract was specifically defined as a ‘condition’. The term provided that over a long period, one of two named representatives of the Client would visit the Company every week. There was no provision to substitute other representatives and no provision for the Company to say a visit was inconvenient. One week the Company did not receive a visit as agreed and sought to terminate the contract.

Which ONE of the following statements best describes the legal position?

The term breached was defined as a condition and so the Company was entitled to terminate for any breach (however small).

The parties could not have intended the particular term to be a ‘condition’ in the legal sense and so damages would be the only remedy for breach.

Commercial contracts cannot be terminated for breach of a condition if the breach is so slight it would be unreasonable to terminate.

As the contract was between two companies and had been reduced into writing and signed the definition of the term as a ‘condition’ would be conclusive.

Terms in contracts drafted by non-lawyers are neither conditions nor warranties: the remedy for breach will always depend on the seriousness of the breach.

A

B is the correct statement. On the face of it the contract had not been drafted by a lawyer and the parties must have known the term would be breached at some time or another. Consequently, they could not have intended one breach to justify terminating the contract- Schuler v Wickman.

The fact the term had been defined as a condition would not be conclusive in the circumstances; hence statements A and D are wrong.

Statement C- a very slight breach of a condition is only a bar to rejecting goods in a commercial contract for the sale of goods (s15A Sale of Goods Act).

Statement E is wrong. As a matter of construction particular terms may have been intended to be warranties or conditions in the strict legal sense.

20
Q

Which ONE of the following statements is WRONG?

If a contract is frustrated it is voidable.

If a contract is frustrated neither party will be in breach.

If a contract is frustrated it terminates automatically at the time of the frustrating event.

If a contract is frustrated neither party need perform any future obligations.

A

A is incorrect. A frustrated contract is not voidable – it comes to an end automatically at the time of the frustrating event and neither party need perform future obligations. All the other statements are correct.

21
Q

Which ONE of the following cases illustrates that a party cannot rely on ‘self-induced’ frustration?

Krell v Henry

Herne Bay v Hutton

Davis Contractors v Fareham UDC

The Super Servant Two

A

the correct answer is D. Here the contract was not frustrated because the court said that the defendants had a choice

22
Q

Is the following statement TRUE or FALSE?

In the case of Metropolitan Water Board v Dick Kerr the contract was not frustrated by the government intervention because the parties had put a ‘force majeure’ clause in their contract.

A

the statement is false. Although the parties had put a force majeure clause in their contract dealing with delay, the court decided that the clause was not intended to cover the event that had occurred.

23
Q

Which ONE of the following statements is CORRECT?

A lease of land can never be frustrated.

A lease of land for less than two years can never be frustrated

A lease of land for any period may be frustrated.

A lease of land can only be frustrated if there are at least 3 years left to run on the lease.

A

C is the correct answer. The House of Lords case of National Carriers Ltd v Panalpina Ltd (1981) established that a lease of land could be frustrated but that this would not be a common occurrence.

24
Q

Julie hired a holiday cottage, ‘Field View’, from Holiday Letts Ltd. for the month of August for £2,000. Julie paid £200 immediately and agreed to pay the balance of £1,800 on 31 August. Holiday Letts agreed to put locks on all of the cottage windows. On 5 August the cottage was destroyed by fire. Holiday Letts had spent £250 on fitting the window locks.

Assuming that the contract is frustrated and the Law Reform (Frustrated Contracts) Act (LR(FC)A) 1943 applies, which ONE of the following is CORRECT?

Julie will still have to pay the £1,800 due on the 31 August.

Under s1(2) of the LR(FC)A Holiday Letts can keep the £200 Julie paid on the making of the contract and Julie will have to pay a further £50 to cover the expenses incurred by Holiday Letts.

Under s1(2) of the LR(FC)A Julie could get back the £200 she paid on making the contract and would not have to pay anything to Holiday Letts for the expenses they incurred.

As Holiday Letts incurred expenses in performing the contract then under s1(2) of the LR(FC)A the court may allow Holiday Letts to retain some or all of the £200 Julie paid on making the contract

A

D is correct. If a contract is frustrated the parties are discharged from future obligations so Julie does not have to pay the £1,800. Section 1(2) of the LR(FC)A1943 provides that a court may allow a party who has incurred expenses in performing the contract to recover some or all of these but only out of money paid or payable before the frustrating event. So here the court may allow Holiday Letts to retain some or all of the £200 but this is the maximum they can get.

25
Julie hired a holiday cottage, 'Field View', from Holiday Letts Ltd. for the month of August for £2,000. Julie paid £200 immediately and agreed to pay the balance of £1,800 on 31 August. Holiday Letts agreed to put locks on all of the cottage windows. On 5 August the cottage was destroyed by fire. Holiday Letts had spent £250 on fitting the window locks. Is the following statement TRUE or FALSE? Under s1(3) of the LR(FC)A the court could order Julie to pay a just sum for the period she has had the cottage if it amounts to a valuable benefit.
The statement is true.
26
Section 1(2) of the LR(FC)A 1943 gives the court a discretion to allow a party who has incurred expenses in the performance of the contract to retain or recover all or some of these expenses out of money paid or payable to him before the frustrating event. Which ONE of the following statements is CORRECT? When exercising its discretion under s.1(2) the court should order total retention of expenses incurred provided these do not exceed the amounts paid or payable before the frustrating event. When exercising its discretion under s.1(2) the court has a broad discretion to do what is just in the circumstances. When exercising its discretion under s.1(2) the court should split the loss between the parties so that there is equal division.
The correct answer is B - the court has a broad discretion. The different ways of exercising the discretion were discussed in the case of Gamerco (1995
27
Is the following statement TRUE or FALSE? When assessing whether or not a valuable benefit has been conferred for the purposes of s1(3) LR(FC)A the court is not concerned with the end product so much as the time and expense involved in producing it.
BP Exploration v Hunt is authority for the principle that the court has to consider the end product
28
Is the following statement TRUE or FALSE? It is possible for the parties to a contract to exclude the LR(FC)A and to make their own provision about the effects of frustration on their contract.
the answer is true - s2(3) LR(FC)A
29
Which ONE of the following statements is WRONG? If the terms of an agreement are uncertain the contract will be terminated and the parties will be released from any future obligations. The terms of an agreement must be certain in order for there to be a binding contract. An agreement can be sufficiently certain if it lays down how the terms can be clarified. Where parties have had dealings in the past, their previous agreements may be used to clarify seemingly uncertain terms.
Statement A is wrong. If the terms of an agreement are uncertain there cannot be a binding contract: the contract will be void. All the other statements are correct. Statement B - a case in which a contract was held to be void for uncertainty is Scammell v Ouston. Foley v Classique Coaches is authority for Statement C and Hillas v Arcos is authority for Statement D
30
A client, a music festival organiser, entered into a contract with a famous rock star to perform on the opening day of a particular festival. The agreed fee was £60,000, including £10,000 payable in advance. A week before the festival the rock star was strongly advised on medical grounds to cancel all imminent engagements. The rock star felt well enough to perform but was finally persuaded by his partner to follow the medical advice and terminated the contract with the client. At such short notice the client could not find a comparable replacement performer for the festival and is demanding compensation for breach. The rock star alleges the contract was frustrated. Which ONE of the following statements best describes the common law position as between the rock star and the client? It was the rock star’s decision not to perform so the client will be entitled to return of the advance payment in restitution and damages for breach of contract. Their contract was frustrated and so the advance payment should be returned and the balance of the fee does not have to be paid. Illness did not make performance of the contract impossible: the rock star can keep the advance payment but is not entitled to be paid the balance. The contract was automatically terminated by the illness and so the client is relieved from paying the balance of the fee; but cannot recover £10,000 paid. The contract was frustrated by the rock star’s illness and is therefore void.
Statement B best describes the common law position. The contract is likely to have been frustrated by the illness being unforeseen, without fault and making performance impossible (Condor v The Barron Knights). The advance payment would be repayable as there appears to have been a total failure of consideration and the balance payable would cease to be payable. This also explains why Statement C is wrong. Statement A – as the client had been strongly advised to cancel the performance the decision not to perform is unlikely to be regarded as a breach. Statement D – frustration does automatically terminate the future performance of the contract and so the client would be relieved from paying the balance of the fee. However, the client would be able to recover the advance payment if, as there appears, there has been a total failure of consideration by the rock star. Statement E is wrong as frustration does not make a contract void.
31
A client owns a warehouse and agreed to let it on terms including the following: RENT : £200 per month payable in advance on the first day of each month TERM : One year from and including 1 March ROOF : Landlord to repair the roof within first two weeks of the Term The tenant paid the rent on 1 March and the client carried out the repairs to the roof at a cost of £500. Then on 2 April the warehouse was completely destroyed by an accidental fire and will take at least 10 months to repair. The tenant had not paid the rent due on 1 April. Which of the following statements describes the most likely legal position? The tenant will be liable to pay the rent for the full term as a lease of land cannot be frustrated. The lease will come to an end as a matter of law but the tenant will be liable for breach of contract if he does not pay the rent that was due on 1 April. If the client sues the tenant for non-payment of rent the tenant may claim the contract is frustrated. If the contract is frustrated the tenant must be refunded £200 rent paid in March and the client will be entitled to £500 to cover the cost of repairing the roof. If the contract is frustrated neither party will be in breach and they can elect to treat the contract as at an end.
C is correct. Whether the contract is in fact frustrated would depend on whether there was a valid force majeure clause or the lease otherwise including an express provision on the matter. A is wrong as a lease of land may be frustrated eg if the event/change of circumstances makes performance totally different. B is wrong. If a contract is frustrated both parties are released from future obligations as a matter of law and neither party will be liable for breach. D is wrong. Repayment of expenses incurred is at the discretion of the court and the most the landlord would be entitled to here is £400 (ie the total paid and payable by the tenant at the time of the frustrating event. E is wrong because if a contract is frustrated the contract automatically comes to an end.
32
A client hired a holiday cottage from a company for the month of August for £2,000. The client paid £200 immediately and agreed to pay the balance of £1,800 on 31 August. The company agreed to put locks on all of the cottage windows. On 8 August the cottage was destroyed by fire. The company had spent £250 on fitting the window locks. Assuming that the contract is frustrated, which one of the following best describes the client’s legal position? The company can keep £200 paid in advance and the client will have to pay the £1,800 due on the 31 August or otherwise be in breach of contract. The company can keep the £200 the client paid on the making of the contract and the client will have to pay a further £50 to cover the expenses incurred by the company. The client can get back the £200 she paid on making the contract and would not have to pay anything else to the company. The court may allow the company to retain some or all of the £200 the client paid on making the contract and award a just sum for the use of the cottage. The client will have to pay £500 for the benefit of having used the cottage and contribute a reasonable sum towards the expenses incurred by the company.
D is correct. Under s1(2) of the Law Reform (Frustrated Contracts) Act 1943 (there is nothing in the facts to suggest that this Act does not apply) a court may allow a party who has incurred expenses in performing the contract to recover some or all of these out of the total money paid and payable before the frustrating event. Also under s1(3) a court should award a ‘just sum’ for any benefit incurred taking into account any money forfeited under s1(2) and the effect the frustrating event had on the benefit. The client had enjoyed 7 days full use of the cottage. A is wrong because if a contract is frustrated the parties are discharged from future obligations so the client does not have to pay the £1,800. B and C are wrong. Section 1(2) of the Law Reform (Frustrated Contracts) Act 1943 provides that a court may allow a party who has incurred expenses in performing the contract to recover some or all of these but only out of money paid and payable before the frustrating event. So here the court may allow the company to retain some or all of the £200 but this is the maximum they can get. E is wrong. A just sum for the use of the cottage may not be £500 and in relation to the expenses incurred the most the court could award would be £200 but up to that sum the court would have complete discretion.
33
A company regularly supplies specialist industrial equipment to a power station on the north west coast of the UK. Under the terms of the contract all deliveries must be made by rail for reasons of safety. Prolonged heavy rainfall and sudden flooding has collapsed the railway bridge nearest the power station and the railway is closed for repairs. No other rail access is available, but delivery by sea might be possible. There is no force majeure clause in the contract covering what has happened. Which of the following options best describes whether or not the contract has been frustrated? Prolonged rain and flooding are predictable events and consequently the contract has not been frustrated. As the the contract did not include a force majeure clause the company will be liable for breach of contract if it does not deliver the goods. The contract would not be frustrated. Closure of railways is a foreseeable event of the sort a supplier should have in mind when entering a contract for the supply of goods; therefore the contract is not frustrated. Closure of the railway was not provided for in the contract and delivery of the goods in accordance with the contract is now impossible The defence of frustration is available. Whether or not closure of the railway was foreseeable, using sea transport means performance of the contract is possible. The defence of frustration will not be available.
Option D is correct because the specific events had not been foreseen and performance of the contract has been rendered impossible. Options A and C are wrong because the prolonged rain, flooding and closure of the railway ad not been provided for in the contract and performance is now impossible. Option B is wrong because non inclusion of a force majeure clause in itself would not render the supplier liable for breach. Option E is wrong because the contract specifically provides for rail transport and so performance is now impossible.
34
A contract is made between a seller and a buyer for the sale of a cargo of cement for the sum of £20,000. Both the seller and the buyer are in business. Following delivery by the seller, the buyer purported to terminate the contract and refused to pay the price. The seller sued and the buyer relied in its defence on a severe economic downturn that affected its ability to make the necessary financing arrangements and (in the alternative) on a Force Majeure clause in the contract that provided “Neither party shall be liable to the other as a result of any failure to perform its obligations due to industrial disputes, government action, default by suppliers, acts of God, and/or national or international calamity.” Will the buyer succeed in its defence? Yes, because the buyer is able to rely on the doctrine of frustration and the Force Majeure clause applies here whether or not it is reasonable. Yes, because the buyer is able to rely on the provisions of the Force Majeure clause and the clause is reasonable. Yes, because the seller is unable to prove that the Force Majeure clause cannot be construed in favour of the buyer. No, because the buyer is unable to rely on the doctrine of frustration or on the Force Majeure clause, whether or not the clause is reasonable. No, because although the buyer is able to rely on the Force Majeure clause, the buyer cannot rely on the doctrine of frustration.
Option D is correct. The buyer is unlikely to succeed in its defence on the facts because a change in economic circumstances is not generally regarded as an event which gives rise to the doctrine of frustration and it does not fall within the terms of the Force Majeure clause. It does not fall within any of the specific events provided for. As a result, the other Options are wrong. There has been no event which gives rise to the doctrine of frustration and the buyer is unable to rely on the Force Majeure clause. (The party who wants to rely on a force majeure clause has the onus of proving that it works as a matter of construction and is reasonable – Option C therefore is also wrong for this reason.)
35
A woman agreed to hire a caravan from a man for four months beginning on 1 July to travel around the United Kingdom. The total cost of hire is £2,000. The woman paid a deposit of £500 and agreed to pay a further £500 on 1 August and the remaining £1,000 on 1 October. They agreed that the man would partly furnish the inside area of the caravan to suit the woman’s needs. The man spent £500 on adapting the kitchenette area and a new mattress. On 20 July the caravan was completely destroyed by fire. As a result of the fire the contract between the woman and the man is frustrated. Which of the following best describes the financial consequences of that frustrating event? The woman does not have to pay the remaining £1,500, but she cannot claim back anything she has already paid as the frustration of contract only discharges future obligations. The woman does not have to pay the remaining £1,500, and she can claim back the money that she paid before the frustrating event in full, being the £500 deposit with no deductions. The man can claim compensation for the expenses he incurred on furnishing the caravan which means he can recover £500. The woman does not have to pay the remaining £1,500, and she can in theory claim back the money that she paid before the frustrating event in full, but the court is likely to deduct the man’s expenses in furnishing the caravan, with the result that neither party receives anything. As the woman had a use of the caravan for approximately 20 days the court could decide that this usage constituted a valuable benefit for which the woman should pay a just sum. It is likely that this just sum will be calculated by reference to the daily hire rate for the caravan.
Option E is the best answer. As the contract has been frustrated, the Law Reform (Frustrated Contracts) Act 1943 will likely govern the financial consequences as follows: The woman can recover any money already paid under the contract and (as a matter of common law) is discharged from paying any further monies. Option A therefore is wrong. However, the man may be entitled to recover his expenses in furnishing the caravan up the value of any monies paid and payable by the woman (which in this case is £500). Practically, therefore, the man is likely to deduct his expenses of £500 from the money he would otherwise have to refund to the woman, with the result that (so far) neither party has to pay any money to the other. Option B therefore is wrong in failing to address the man’s likely ability to recover his expenses; option C is wrong in failing to address the fact that the money already paid by the woman has to be set off against any compensation the man might receive. The reason why option D is not the best answer is that the woman’s usage of the caravan for 20 days before the frustrating event is arguably a valuable benefit in respect of which the court can (in its discretion) award a just sum. That sum is likely to be calculated by reference to the daily hire rate of the caravan. Working through the 1943 Act therefore means that practically the woman’s right to recover money already paid and the man’s potential ability to recover compensation for expenses cancel each other out, with the result that the only item that becomes payable is a possible just sum for the woman’s usage of the caravan.
36
In January a woman agrees with an owner to hire his hotel for her 60th birthday party in June. The woman pays the first instalment of £2,000 immediately. She agrees to pay a further £3,000 eight weeks before the party and a final payment of £5,000 one month before the party. The owner agrees to purchase a temporary indoor water fountain for the party. Seven weeks before the party the hotel is struck by lightning and the resulting fire destroys the building. It will take 12 months to repair the hotel and therefore the party cannot take place in June. The woman has not paid the second and third instalments. The owner has paid £800 for the water fountain which was destroyed in the fire. Assuming the contract has been frustrated by the fire, which of the following statements best describes the powers of the court to do justice between the parties? The woman will not be required to pay the second and third instalments and the owner must return the first instalment subject to the deduction of a fair sum for purchasing the water fountain. The owner can keep the first instalment and the woman will be required to pay the second instalment because all of this money was due before the fire happened. As there has been a total failure of consideration the owner must return the first instalment and the woman does not have to pay the other two instalments. The woman must pay £800 for the benefit she obtained under the contract and, having retained this sum, the owner must return the balance of the first instalment. The woman must pay the agreed sum of £10,000 for the hire of the venue. The owner will keep the first instalment and the woman will be required to pay both of the outstanding instalments.
Option A is correct. In the event of frustration of a contract the contract is automatically terminated at common law and the parties are discharged from future obligations. This means that the woman will not have to pay the final instalment. The Law Reform (Frustrated Contracts) Act 1943 (the Act) regulates what is to happen in relation to money paid or payable before frustration and expenses incurred before the frustrating event: Under s1(2) of the Act money paid must be returned. The first instalment must be repaid. Money payable before frustration, but not yet paid, need not be paid. The second instalment need not be paid. If the recipient of that money (the owner)incurred expenses in performance of the contract (£800 for the water fountain)then the court has an absolute discretion to award a fair sum out of the tot of money paid and payable before frustration (£2,000 + £3,000 = £5,000). The court may order the owner to receive a fair sum (likely no more than the £800 spent on the water fountain). Subject to that he would have to return the balance of the first instalment and the woman would not have to pay the second instalment. The woman does not have to pay the third instalment under the common law. Option B is not the best answer. Under the 1943 Act, monies paid before the frustrating event are generally returned to the paying party, and monies payable before the frustrating event need not be paid. As the owner’s expenses are only £800 it is not likely that the fair sum the court may order to cover the owner’s expenses will exceed this sum. As a result, that sum can be met by deductions from the first instalment, and it is unlikely that the woman will be ordered to pay any of the second instalment. Option C is not the best answer. There has been a total failure of consideration but this is due to frustration and the Act provides that there is a possibility that the owner may receive a fair sum for expenses he incurred under the contract. The court may order a fair sum to be paid to the owner out of the first instalment (and possibly, but unlikely, out of the second instalment). Option D is wrong. Under s1(3) of the Act a court can order someone who has received a benefit under the contract to pay a fair sum for that benefit. However, the woman has not received any benefit as the hotel was destroyed before the party. Option E is wrong. Given the contract has been frustrated, the second and third instalment will not need to be paid and the first instalment will be returned (subject to the award of a fair sum for expenses).
37
A contract for the hire of a fishing boat (‘the Boat’) was entered into between the boat owner and a fishing company. It was an express term of the contract that the Boat could only be used for fishing. The Boat could only operate using a certain type of fishing net, the use of which had to be licensed by the relevant government department. The fishing company owned four similar vessels that it intended to operate using the same type of fishing net. After entering into the contract, but before the Boat was delivered by the boat owner, the fishing company applied to the government department for five licences. However, the government only granted three licences and the fishing company applied those licences against three of its own vessels. The fishing company now claims that it is no longer bound to take delivery of, and pay hire for, the Boat. Can the fishing company rightly claim that they are no longer bound to take delivery of the Boat? Yes, because the government’s refusal to grant five licences has made it impossible to use the Boat. Yes, because it is fair in all the circumstances for the fishing company to refuse delivery of the Boat. Yes, because the government’s decision to only grant three licences could not have been foreseen when the contract was entered into. No, because the fishing company agreed to hire out the Boat and it is irrelevant if the use of the Boat as a fishing vessel is now impossible. No, because it was the fishing company’s choice not to apply one of the licences against the Boat.
Option E is correct. It is impossible or illegal to use the Boat without a fishing licence. In order for this to be a frustrating event (thereby allowing the fishing company to refuse delivery of the Boat), the fact that the Boat is not licensed must be beyond the control of the parties. However, a party whose own act or election has given rise to the frustrating event cannot rely on the doctrine of frustration. In this case, it was the fishing company that decided to apply the three licences against vessels other than the Boat. It was their act therefore that made it impossible to use the Boat. As a result, their refusal to take delivery of the Boat will put them in breach of contract. Option A is wrong. It is not the government’s refusal to grant five licences that has made the use of the Boat impossible, but rather the fishing company’s decision to apply the three licences granted against other vessels. Option B is wrong. Whether or not it would be fair to excuse one party from their obligations is generally irrelevant. If that party has promised to do something, the court will generally enforce that promise. Option C is wrong. It might be true that the government’s decision to only grant three licences could not have been foreseen. However, given the fishing company’s decision not to apply the licences granted against the Boat, this is irrelevant. Option D is not the best answer. This option states the original common law rule that parties would still be liable even if the performance of absolute obligations had been rendered impossible by subsequent events. This strict rule has been tempered by the doctrine of frustration. However, frustration does not operate in this particular case.