Purpose of Cost Estimation
Phasing of Cost Estimates
I & R
Investigation and Reporting
PFR
Project Feasability Report
D & PD
Design and Project Documentation
Accuracy of Estimate at Concept Stage
+/- 50%
Accuracy of Estimate at Pre-Feasability
+/- 30%
Accuracy of Estimate at Feasability
+/- 25%
Accuracy of Estimate at Preliminary Design
+/- 20%
Accuracy of Estimate at Detailed Design
+/- 15%
Accuracy of Estimate at Tender Price
actual price + variation
Capital Cost Estimate could include:
CAPEX
Capital Expenditure
Design Fees
Preliminary-Technical Studies
Detailed Design
Field Investigations
Approvals
General Items in “Bill of Quantities”
approx. 15% of project cost
- P & G
- Mobilisation
- Management Plans and Submittals
- Misc.
- Demobilisation
Specific Items in “Bill of Quantities”
Operating Cost Estimate could include:
OPEX
Operating expenditure
NPV
Net Present Value
Engineers Estimate