EF - Early Finish =
EF = ES + D - 1
ES - Early Start =
ES = EFp + 1
LS - Late Start =
LS = LF - D + 1
LF - LAte Finish
LF = LSs - 1
FF - Free Float
FF= ESs - EF - 1
TF - Total Float
TF = LF - EF
Subscripts - s and p
s = Successor p = Predecessor
ID & D
ID = Activity ID D = Duration in days