Precedence Table
Has the activities listed in the left column and their dependencies on the right.
Creating an activity network
Start with a node labelled 0
Point arcs representing activities that aren’t dependent on any others from there
Label each node with an increasing number. connect multiple arcs where one is dependent on multiple
Connect the terminating activity/activities to a sink node at the end
Arcs must be straight
Dummy Arcs
Dotted lines from a node to another to show that the activity that is dependent on is needed for the one on the other end of the dummy
When do you need a dummy arc?
Early event time
The earliest time a project can be started based on all events it is dependent on being completed
Late event time
The latest time a project can be started without extending the time needed for a project
Finding early and late event times
Trace forward from the source node for early, the latest time a needed event is completed
Trace back from the sink for the late, the earliest time from this
Critical activity
Any increase in its duration will increase the duration of the whole project
Early start time = late start time where the values on the next node are equal to the values on that node plus the length of the activity
Critical path
A path from the source node to the sink node that exclusively follows critical activities
Float of an activity
The amount of time that its start may be delayed without affecting the duration of the project
Float of an activity formula
latest finish time - duration - earliest start time
Gantt Diagram
Shows the time each activity can be completed in visually using a diagram with rectangles for each activity
Critical activities Gantt diagram
Rectangles across one line for all of them connected
Non-critical activities Gantt diagram
Draw a rectangle from the early start time with length the duration. Draw a dotted rectangle from there to the late time.
Each should have a new line
When an activity must be at a time Gantt diagrams
No matter how far through the float it is shifted the rectangle will always encompass that time
Day 10 Gantt diagram
Between lines 9 and 10
Resource histograms
Scheduling diagram
Looks like a Gantt chart
Lower bound for the amount of workers required
Sum of all the activity times / critical time of the project and round up to the nearest whole number
Where the workers is fewer than the lower bound
Make a scheduling diagram from the activity network by inspection to minimise the run-time. Check for dependencies