What is CPA
A widely-used project management tool that uses network analysis to help project managers to handle complex and time-sensitive operations in the most efficient way
CPA model includes
What does CPA calculate
What is a node
A circle on a CPA that represents a point in time where an activity is started or finished. The node is split into 3 sections
What is the left half of a node
The unique node (activity) number - the network diagram draws these in order
What is the top right section of a node
Shows the earliest start time (EST) that an activity can commence based on the completion of the previous activity
What is the bottom right section on a node
Shows the latest finish time (LFT) by which the previous activity must be completed
How is an activity shown on a CPA
By linking the nodes with a line. A letter representing the activity is usually shown above the relevant line
How is the duration of an activity shown on a CPA
Under the activity line - below the letter of activity
Advantages of CPA
Disadvantages of CPA
how to calculate float
latest finishing time - duration - earliest starting time