Critical path analysis
On forward passes
On the left hand box, take the larger choice
On the backward pass
On the right side, choose smaller choice
Total float =
Late finish - early start - duration
Independent float =
Early finish - late start - duration
Interfering float =
Total float - independent float
Cascade diagrams
Resource histogram:
Use the cascade chart to count the number of workers needed on each day
Y axis = number of workers
X axis = days
Why use critical path analysis?
Allow project managers to handle complex and time sensitive operations, and organise scheduling of workers and days