What does CPA stand for?
Critical Path Analysis
What do you have to do to be able to undertake CPA?
What does CPA entail?
Which process calculates the timeframe in which activity takes place?
Time analysis
What are the five steps of time analysis?
How do you carry out forward pass? (Calc)
Forward pass = (ES +duration) -1
How do you carry out backward pass? (Calc)
Backward pass = (LF - duration) + 1
How do you work out each activities’ free float during time analysis? (Calc)
Free float = (LF - EF) + (LS - ES)
What’s lead?
Negative lag
Why are constraints not good planning practice?
Because activities should ideally be linked through logic
What are the four key stages of managing project interfaces?
What structures help identify project interfaces? (3)
Who must be identified during project interface management?
Key stakeholders who are likely to impact the critical path
What are the two primary methods for integration and impact analysis?
What falls under internal integration?