what does a precedence/ dependency table show?
a table which shows which activities must be completed before the others are stared
what does a dummy activity show?
dependencies between activities
does a dummy activity have weight?
no
at most how many activities can there be between any two events?
one
what does a late event time do?
latest time can be left without extending project time