Critical path analysis Flashcards

(8 cards)

1
Q

What is it?

A

Is a project analysis and planning method that allows a project to be completed in the shortest time poisible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is it needed? (2)

A
  1. If a project is complex and involves significant investment and risk
  2. More complex projects need to be better at identifying relationships between activities and work out the most efficient way to complete a project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Info needed (3)

A
  • List of activities
  • Duration of activities
  • Dependencies (what ones have to be completed first)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4 rules of CPA?

A
  1. EST is calculated first
  2. EST is where 2 or more activities meet (highest figure picked)
  3. LFT is calculated last
  4. LFT is where 2 or more activities meet (lowest figure picked)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Float?

A

= the duration the activity can be extend so that the project can be finished on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

formula for float?

A

LFT - activity duration - EST = total float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens if the float of an activity is 0?

A

Activities with a float 0 can’t be delayed without delaying the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Uses of CPA? (4)

A
  • Estimate a minimse time
  • Supports project costing and evaluation
  • Plan and organise resources
  • Priortise tasks