What is it?
Is a project analysis and planning method that allows a project to be completed in the shortest time poisible
Why is it needed? (2)
Info needed (3)
4 rules of CPA?
Float?
= the duration the activity can be extend so that the project can be finished on time
formula for float?
LFT - activity duration - EST = total float
What happens if the float of an activity is 0?
Activities with a float 0 can’t be delayed without delaying the whole project
Uses of CPA? (4)