What is critical path analysis?
Is a project analysis and planning method that allows a project to be completed in the shortest possible time.
What is a critical path?
The sequence of project activities adds up to the longest overall duration. The critical part of the time is the shortest possible time to complete the project.
Why do businesses need to plan complex projects?
What is the information needed for CPA?
What does the CPA diagram calculate?
What part of the node is the EST?
What part of the node is the LFT?
What part of the node is the node ref?
What part of the CPA diagram is the activity?
What part of the CPA diagram is the duration?
Top right
Bottom right
Left half section
Top of the line at the same level as the EST.
The bottom half of the line is at the same level as the LFT.
What are the 4 golden rules of a CPA diagram?
How do you calculate the float time?
The float time is the duration an activity can be extended or delayed so that the project still finishes within the minimum time.
Calculated as:
LFT- EFT
How do you calculate the LFT?
How do you identify the critical path?
Activities with a float of 0 cannot be delayed without delaying the entire project. Such activities represent the critical path. On the critical path, activities are equal EST and an LFT and zero float.
What are the uses of critical path analysis?
Why is CPA so important?
Any delay activity in the critical path directly impacts of planned project completion date.
What are the advantages of CPA?
What are the disadvantages of CPA?