Define CRITICAL PATH ANALYSIS
Critical path analysis is a technique used to identify the order in which all activities need to be completed when planning a complex project.
Define a CRITICAL PATH
A critical path is the set of tasks that will prolong the duration of the project if delayed.
How is a critical path model drawn?
Define an EST
An EST is the earliest time that a task can start. They go in the top right hand quadrant of the node, to the left of the task.
To calculate: go from left to right, adding the duration of the task to the previous EST.
Define an LFT
An LFT is the latest time that a task can finish without delaying the next task. They go in the bottom right hand quadrant of the node.
To calculate: work from right to left. Subtract the duration of the activity from the previous LFT. If there is more than one answer, write down the lowest result.
Define FLOAT
Float is the spare time that arises between the completion of an activity and the starting time of the next activity.
To calculate: LFT - duration - EST
What are the advantages of critical path analysis?
What are the disadvantages of critical path analysis?