Forward Pass
EF determined by adding the duration to the ES -1
ES of successor tasks = latest EF of predecessor tasks +1
Backward Pass
LS determined by subtracting the duration from the LF +1
LF of predecessor tasks = earliest LS of successor tasks -1
Float (Slack)
LF-EF
Critical Path
the longest duration path through the network diagram. Any delays along the critical path will delay the project.