Start the compressor and allow it to run with air flowing from the sampling point for at least________ before performing air sample test
15 minutes
Slowly open the compressor charging lead or air source valve until a steady pressure in the range of________ is established on the Flow Section Pressure Gauge
4-6 psi
DCAT pressures and corresponding test times
4 psi for____ minutes 5 psi for____ minutes 6 psi for___ minutes
14
12
10
Begin timing the test as soon as_____________(DCAT)
the moisture stain tube is in place
What color does the moisture tube become during DCAT test?
Reddish brown
ALL______ BLANKS MUST BE COMPLETED _______ DATA PROVIDES FLOW TIME REQUIREMENTS________ INFORMATION PROVIDES IMPORTANT WARNINGS
YELLOW
GREEN
ORANGE
3.2.1.3The contractor shall be responsible ior updating the DCAT website with analytical reports twice daily at______ and NLT ________.(DCAT)
noon
I80O CST
Ifthe website goes ofline, the contractor shal have theabilityto restore the website to online service within______.(DCAT)
24 hours
The contractor has_________ upon receiving kits to complete the analysis. Once the analysis is complete the report wil be downloaded to the DCAT website by________.
two (2) working days
noon of the second day