West End Art’s Library - What is a DRA and why is it used?
A design risk assessment (DRA) is a formal process where designers identify, evaluate, and control potential health and safety hazards associated with a project’s design throughout its entire lifecycle.
West End Art’s Library - Follow on from question 1 - Why is it important?
Legal Compliance: Fulfills duties under regulations like the Construction (Design and Management) Regulations 2015 (CDM) in the UK.
West End Art’s Library - How did you manage design risk in a live building?
I managed design risk by preparing a designer’s risk register at pre‑contract stage and embedding mitigation measures into the design for a live public building.
West End Art’s Library - What risks did you identify in the designer’s risk register?
I identified public safety, live‑environment interface risks, and access constraints associated with working in an operational library next to a busy street.
West End Art’s Library - What Guidnace would you refer to?
I referred primarily to my duties under the CDM Regulations 2015, using a designer’s risk register to manage risks in a live public building.
Haymerle School - What is a SoW and how do you produce a schedule of works?
• Refer to British Standards
• Refer to the approved documents
• Consult manufacturers info
• Consult previous specifications
• Look on the NBS
Haymerle School - If you were specifying a flat roof are any other approved documents you would refer to?
• Part A – Structure
• Part B – Fire Safety
• Part L - Passive of Sound
Haymerle School - Who was the specialist roofing supplier and why did you approach them?
Baulder, repuation garentees and compaabiliuty with the existing building
Haymerle School - What is a U-Value and how is it calculated?
• The rate of heat transfer through a building element, such as a window, wall, or roof. A lower U-value means better insulation, as it shows a lower rate of heat loss.
• A U-value is calculated by first determining the total thermal resistance (R-value) of a building element by summing the R-values of all its individual layers and surface resistances.
Haymerle School - Was the flat roof and cold or warm roof, what’s the difference?
• Cold Roof – Insulation layer is below the structural deck and installed between the ceiling joists (Flat Roof).
• Warm Roof – Insulation layer is installed above the structural dec and roof coverings laid on top.
Haymerle School - Describe the roof building up in the warm flat roof design.
Structural Deck
vapour control layor
insulation
waterproofing
Haymerle School - Why did you choose a warm roof construction?
The warm flat roof was best the the exiting constrcution, consideration was made for a cold roof but would have required more insrusve work and changing from the existing design.
Haymerle School - How did you ensure compliance with Approved Document A?
I ensured compliance with Approved Document A by confirming the replacement roof build‑up did not increase loads or alter the existing structural performance and had the propsoed roof check by a structrual engnner.
Haymerle School - How did you ensure compliance with Approved Document B?
I ensured compliance with Approved Document B by specifying a BROOF(t4) roof covering, checking boundary distances, and confirming the works did not compromise fire compartments or means of escape.
Haymerle School - How did you ensure compliance with Approved Document C?
I ensured compliance with Approved Document C by redesigning the roof to achieve design falls of 1:40 and a minimum finished fall of 1:80, preventing ponding and moisture ingress.
Haymerle School - What Guidnace would you refer to?
I referred to the relevant Approved Documents, BS 6229 for flat roof design, manufacturer guidance, and CDM 2015 to ensure the works were compliant and robust.