When does directing a project run form and to?
End of the starting up project and until very end of. close down of project
Which party is within Directing a Project
the project board
What should the Project Board do during Directing project?
1) Manage by exception
2) Monitor through reports
3) Control through a series of key decision points
What are the activities during directing of a project?
1) Authorise initiation
2) Authorise the project (PID)
3) Authorise a stage or exception plan
4) Gice ad hoc direction
5) Authorise project closure