Drawings take precedence over specs true or false?
False. Neither takes precedence. They are complementary. IF THERE IS A CONFLICT THE ARCH SHOULD BE NOTIFIED!!
Specs are organized into _______ and cover _________
2. General, materials and execution
The specifications are part of the ________ . And are legal documents T of F.
2. True
AIA Document A701
Instructions to bidders
4 major parts of Project Manual
Bidding Requirements
Parts of Contract
Conditions of Contract
Technical Specifications