PMP Exam Prep > Earned Value Management (EVM) > Flashcards
Which EVM formula should be used to calculate a forecast?
EAC (Estimate at Completion)
What is CV?
What is CPI?
CPI of 0.9 = Project is 10% over budget
What is SV?
What is SPI?
SPI of 0.7 = Project is 30% behind schedule