SOW is?
Statement of Work
WBS is?
Work Breakdown Structure
What work is to be performed
What kind of account is used to accumulate costs?
Control account
or
Cost account
All tasks that will charge to a control account are called a?
A work package
All tasks in a work package are planned in a detailed _____ ?
Schedule
A WBS can be viewed as an org chart and breaks down what?
The work to be performed into explicit areas and sub-areas
What is an OBS?
Organizational Breakdown Structure
Tells WHO is responsible for the work to be performed
What is a RAM?
A Responsibility Assignment Matrix.
Typically, Control accounts are matrixed to facilitate accumulation of costs by both task and performing organization
Define BAC
Budget at Completion – it is our target
ETC is?
Estimate To Complete
EAC is?
Estimate At Complete
Sum of ACWP + ETC
BAC is?
Budgeted At Complete
VAC is?
Variance at Completion
BAC - EAC = VAC
TRUE / FALSE :
Both Cost Tracking and Performance Measuring are provided by EVMS
TRUE
BCWS
Budgeted Cost of Work Scheduled
BCWP
Budgeted Cost of Work Performed
ACWP
Actual Cost of Work Performed
EVMS is a system that helps you do what four tasks?
Cost Variance CV is calculated how?
favorable is positive
CV = BCWP - ACWP
CV% = CV / BCWP
Schedule Variance SV calculated how?
favorable is positive
SV = BCWP - BCWS
SV% = SV / BCWS
Variance at Completion (VAC) calculation?
favorable is positive
VAC = BAC - EAC
Cost Efficiency – CPI calculated how?
favorable is > 1.0
CPI = BCWP / ACWP
Schedule Efficiency – SPI calculated how?
favorable is > 1.0
SPI = BCWP / BCWS
Percent Complete calculation?
BCWP cum / BAC