ele510-everything ordered Flashcards

(109 cards)

1
Q

What is the formula for ES and EF in a network diagram?

A

ES = max(EF of predecessors); EF = ES + Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula for LS and LF?

A

LF = min(LS of successors); LS = LF − Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is float in a network diagram?

A

Float = LS − ES

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What defines a critical path?

A

All activities with float = 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How to find project duration?

A

Largest EF in final activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the meaning of float = 0?

A

Activity cannot slip without delaying project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four dependency types?

A

FS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is fast tracking?

A

Overlapping activities to shorten schedule (increases risk)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is crashing?

A

Adding resources to shorten duration (increases cost)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CPIF fee formula

A

Fee = TF + (TC − AC) × SC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CPIF price formula

A

Price = AC + Fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

CPIF AC where fee = max fee

A

AC = TC + (TF − Fmax) / SC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CPIF AC where fee = min fee

A

AC = TC + (TF − Fmin) / SC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

FPI profit formula

A

Profit = TP + (TC − AC) × SC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

FPI price formula

A

Price = AC + Profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Target Price formula

A

TPrice = TC + TP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

PTA formula

A

PTA = (PC − TPrice) / SO + TC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

AC where profit = 0 (FPI)

A

AC = TC + TP / SC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Who holds risk in Firm Fixed Price contracts?

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Who holds risk in Cost Plus Fixed Fee contracts?

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Who holds risk in CPIF and FPI?

A

Shared according to share ratio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

NPV formula

A

NPV = Σ CFₜ/(1+r)ᵗ − Initial Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
NPV decision rule
Accept if NPV > 0
26
Cost of equity (CAPM)
re = rf + β (rm − rf)
27
WACC formula
WACC = (E/V)re + (D/V)rd(1−T)
28
Profitability Index formula
PI = PV of future cash flows / Initial Cost
29
Profitability Index decision rule
Accept if PI > 1
30
Payback period definition
Time until cumulative cash flows become positive
31
IRR definition
Discount rate that sets NPV = 0
32
IRR decision rule
Accept if IRR > required rate
33
34
Define PV in Earned Value
PV = Planned Value (planned work)
35
Define EV in Earned Value
EV = Earned Value (completed work)
36
Define AC in Earned Value
AC = Actual Cost (cost spent)
37
Cost Variance formula
CV = EV − AC
38
Schedule Variance formula
SV = EV − PV
39
CPI formula
CPI = EV / AC
40
SPI formula
SPI = EV / PV
41
Interpret CPI < 1
Over budget (bad)
42
Interpret SPI < 1
Behind schedule (bad)
43
EAC formula (most used)
EAC = BAC / CPI
44
VAC formula
VAC = BAC − EAC
45
46
Risk exposure formula
Risk Exposure = Probability × Impact
47
What is an iso-risk line?
Different risks with equal exposure
48
What are the 6 risk responses?
Accept
49
What is a contingency plan?
Predetermined backup plan for identified risks
50
Difference between risk and hazard
Risk = probability × impact; hazard = source of harm
51
52
Four phases of the project life cycle
Concept → Planning → Execution → Close-out
53
What is fast tracking vs crashing?
Fast = overlap tasks; Crash = add resources
54
What is a milestone?
A significant point/event with zero duration
55
Difference between Gantt early vs late start
Early = ASAP scheduling; Late = latest start without delay
56
Difference between network diagram and Gantt
Network shows logic; Gantt shows timeline
57
58
PBS definition
Product Breakdown Structure = deliverables
59
WBS definition
Work Breakdown Structure = tasks/work packages
60
OBS definition
Organizational Breakdown Structure = who is responsible
61
Purpose of a WBS
Basis for cost estimation and scheduling
62
PBS vs WBS
PBS = what; WBS = how
63
64
Power–Interest Matrix: High power/high interest
Manage closely
65
Power–Interest: High power/low interest
Keep satisfied
66
Power–Interest: Low power/high interest
Keep informed
67
Power–Interest: Low power/low interest
Monitor
68
Salience Model: three attributes
Power
69
Salience: stakeholder with all three attributes
Definitive stakeholder
70
Stakeholder analysis steps
Identify → Classify → Analyze → Plan engagement → Monitor
71
72
Functional structure definition
Departments; PM has little authority
73
Projectized structure definition
PM has full authority
74
Matrix structure definition
Dual reporting lines
75
When to use matrix structure
When resources must be shared across projects
76
What is supply chain management?
Managing flow of materials and services
77
Procurement phases
Planning → Selection → Contracting → Control
78
Difference between T-buy
RFQ
79
80
Systems diagram components
Inputs → Process → Outputs → Feedback
81
Difference between feedback and feed-forward
Feedback = after output; feed-forward = before process
82
What is a system?
Interrelated components working toward a purpose
83
What is a process?
A sequence of activities transforming inputs
84
What is a procedure?
A specified method for performing tasks
85
86
Scoping definition
Defining what is and isn’t included
87
Scope leap vs scope creep
Leap = big sudden change; Creep = small uncontrolled changes
88
SMART framework
Specific
89
Triple constraint (fundamental constraints)
Time
90
Team life cycle
Forming → Storming → Norming → Performing → Adjourning
91
92
Belbin roles examples
Plant (ideas)
93
Conflict resolution: collaborate
Win–win
94
Conflict resolution: avoid
Ignore problem
95
Conflict resolution: force
One side wins
96
Leadership achieving styles
Charismatic
97
98
Quality definition
Conformance to requirements
99
Difference: quality vs grade
Grade = category; quality = correctness
100
Difference: quality vs reliability
Reliability = consistency of performance
101
Cost of quality formula
COQ = Prevention + Appraisal + Failure
102
What is an external failure?
Warranty claims
103
104
Purpose of project control system
Track performance against plan
105
Three types of change in projects
Scope change
106
Who pays for change?
Depends on contract type and responsibility
107
Milestone monitoring definition
Tracking progress using key checkpoints
108
Determinants of project success
Clearly defined goals
109
Determinants of project failure
Poor planning