What is a Conceptual Estimate
What is a Preliminary Estimate
What is an approximate Estimate
What is a detailed bid estimate?
What costs are under Direct vs Indirect costs and how much percent do each take?
Direct cost (65-90%):
- Labour cost
- Material cost
- Equiptment cost
- Subtractor cost
Indirect cost (10-35%):
- Project overhead
- Markup
What are Labor Costs
Direct Labor costs: costs that are paid to field workers
Indirect Labor costs: costs that are additional to direct costs (payroll taxes, insurance, fringe benefits etc), usually = 25-50% of direct labour cost
What are Material costs
All costs in procuring materials (delivery, storage, inspection)
Contractor must:
- produce own materials (use own estimate) OR purchase materials from manufacturer
- include cost for storage, handling and installation of owner supplied or designated materials (excluding cost for purchasing materials)
What are Equipment Costs
All the costs of renting equipment
Diff Cost Rates:
- cost/hour (eg. tractors, scrapers)
- cost/unit installed ( eg. concrete mixing)
- cost/week or month (eg. scaffolds)
Accuracy of cost estimate depends on equipment importance
- Major equip = very detailed analysis
- Minor equip (power tools concrete vibrator) = standard cost allowance
- Minor equip (hand tools, water hose) = lump sum allowance as % of direct labour cost
What are Subcontract Costs
GC subcontractor portions of work to subcontractors
Cost of subcontractors finalized before final bid
GC must review and select SC (like owner selects GC)
What is Project Overhead cost
All costs that don’t pertain directly to construction workers (5-15% total project cost)
Refer to list in pg.17 of Lecture 8
What are Markup Costs
Subjective
Factors:
- desire for work
- competition
- market conditions
- relationship with owner
- magnitude of risks and opportunities