What are the 6 estimating methods?
How do you estimate using the functional unit of accommodation? 2 points
Nr of units x Cost range = Cost
Adjust rate for finishes, location etc.
How do you reverse budget using the functional unit of accommodation?
Budget / Cost per unit = Nr of units
How do you estimate using the floor area method?
GIFA x Cost range = Cost
GIFA - measured at each floor level
What are the advantages and disadvantages of using the floor area method of estimating? 9 points
Advantages
1. Quick.
2. Simple.
3. Ideal for early budgeting purposes.
4. Directly relates to accommodation.
5. Allows for comparisons of different designs.
6. Allow comparisons between buildings that differ in size and shape.
Disadvantages
7. Doesn’t allow for extra ceiling height eg. warehouses. Allowances must be made.
8. Very loose estimation because quantity of key elements do not necessarily increase or decrease per m2 eg. number of walls and doors.
9. Specification adjustments not feasible as quality differentials are element specific.
How do you estimate using the elemental cost per (GFA) m2?
Calculate the proportion of the total cost for each element on a similar building then apply to measure for the new building.
How do you estimate using the elemental unit rate?
Approximate quantity of each element x Unit rate = Cost of each element
Name 6 sources of cost data.
Priorities when selecting cost data? 3 points
What adjustments to source rates must be made? 3 points
What assumptions and exclusions should be included in cost estimates? 9 points
EXCLUSIONS
1. External works / preliminaries.
2. VAT
3. Professional fees.
4. Fittings and furnishings.
5. Land cost.
6. Interest charges.
ASSUMPTIONS
7. Overheads and profit added at 5%
8. Preliminaries added at 10%
9. Contingencies added at 5%
What affects the degree of accuracy of an estimate? 3 points
What are the three adjustment calculations?
Time adjustment = Proposed index / Historical index
Location adjustment = Proposed index / Historical index
Cost x Time x Location = New total
How much contingency should you allow for in an estimation? 2 points
5% on new builds and 10% on refurbishment.
How do you estimate using the approximate quantities method?
Measurements concentrated to a few items as needed, per element. eg cavity wall - same area for external brick facing, cavity, insulation, internal block skin.