How many communications systems are required for FD to CR communication?
2.
Sound powered phones
What will happen if the MX system is lost to the CT fan controls?
Define a safe shutdown earthquake.
Define Operating basis Earthquake.
What provides DC power to the seismic recorder during a loss of local AC power and for how long?
What is the function of the STA with regards to seismic concerns?
How soon must the following be completed:
15 minutes from the first indication.
7 days.
How is a seismic alarm validated for false or real conditions?
An alarm without ground motion felt in the CR is considered a false alarm. This is validated by observing for waves in the FP.
State the requirements found in TLCO 3.3.103
What will cause the seismic digital recorders to begin recording?
Any accelerometer of the 6 forced balanced accelerometers will start all digital recorders.
State the power supplies and what signals will close GAA-UV-1/2.
State the high and low pressure N2 header operating pressures and how each are maintained.
State the HP nitrogen pumps operating characteristics.
How long is the cooldown cycle?
What will block pump start?
State the HP N2 loads.
What is a level 1 evaluation and when is it required to be performed?
Determination of whether an OBE or SSE has occurred and it must be done by the STA within 1 hr.
What is a level 2 evaluation, who performs it and how long do they have to complete it?
Determination of whether an SSE has occurred, done by Civil Engineering and must be completed within 7 days.
What action is required if an OBE has occurred?
What action is required if the seismic event is between 0.01g and OBE?
All units must be shutdown to M.3 and a plant cooldown is required to inspect the SG’s.
System and site walkdowns must be performed on SFP, AFW pumps and piping, RCS leakage evaluated,
State the design basis of the AFW system.
What cools the AFW room coolers and how are they operated?
What is the limit placed on the AFN use
What range of operation is the AF system set to maintain?
What is the D/P lockout associated with the AFAS signals, and which SG is essentially isolated from feed?
What is DAFAS and what setpoints actuate it?
DAFAS or Diverse Automatic Feedwater Actuation System is an independent and redundant backup to the AFAS signals designed to start AFW to any intact SG not receiving feed.
State what will start the class AFW pumps.