SSC payment claim and payment timelines?
SSC:
Day 0: Payment Claim recieved
Day 5: Issue Payment Schedule
Day 8: Principal amendments
Day 10: Issue replacement payment schedule
Day 17: Last day pricipal has to pay
NZS 3910 payment claim and payment timelines?
3910:
Day 0: Payment Claim recieved
Day 7: Issue Payment Schedule
Day 10: Principal amendments
Day 12: Issue replacement payment schedule
Day 17: Last day pricipal has to pay
What advice should you give to the clients at practical completion?
What advice should you give to the contractor regarding practical completion?
What happens next?
- Adjust bank guarantees or bonds, notify clients, and ensure the contractor provides requested information.
What information should you give to the client regarding Defects?
What information should you give to the contractor regarding Defects?
What does practical completion mean?
That the works can be used for their intendd purpose.
This excludes work that is: deffered, minor omission and defects
Who should you not issue practical completion to?
Not to third parties (no one that is not in the contract!!!)
ie. a purchaser shouldnt be issued the practical completion document to purchase a property
The contract notes that “The certificate cannot be relied on for any other purpose.” and “They are NOT issued to any other
party and cannot be relied upon by any other party.”
Can you bring an outside expert to certify Practical Completion?
NO - The Architect can bring outside expertise in but the authority of the final decision/power rests with the Architect
What should you do if someone pressures you to issue PC?
Never issue such certificates prematurely under pressure from anyone.
When does the DLP start?
The Defects Liability Period is the period stated in the Specific Conditions of Contract. It commences from the date on which the Contractor achieved Practical Completion and continues for the stated period ending when the Contractor has completed all omissions, corrected all defects and completed all deferred work.
Can you issue PC with conditions attached?
No - Practical Completion and Defects Liability Period certificates cannot be issued “subject to” or “conditional on” completion of listed items.
a list can be attached listing the minor omissions, minor defects and deferred work that has been agreed with the Contractor. This list is consistent with the definition of Practical Completion.
What do you need to do if you Payment Schedule does not match the Contractors Claim?
be sure to give adequate reasons
What action should members take regarding clients and slow payment or short-payment, and what potential consequences should clients be educated about?
Members should educate Clients about the consequences of slow payment or short-payment so that the client may accommodate the risks as they see fit. They may otherwise seek retribution – on the basis of a latent but un-notified risk - when the Contractor walks off the job or stymies on-sale (or financing arrangements) by exercising their rights under the Act.
Do you need Form 1 for non-residential projects?
Yes now you do - I believe it was previously only for Residential projects.
How does CCA apply differently when it comes to residential vs commercial?
Adjudication processros are differnet.
Adjudicators can approve issuing a charging order (enforcement) over a construction site except under a residential construction contract.
Look at PN 9.501
Maybe go through the CCA here in depth. or in the ACTS and SHIT deck
f
What document is required to be issued by the Contractor when making a claim on a residential project under the CCA?
The Construction Contracts Regulations 2003 Form 1 must be issued by the Contractor when making a claim on a residential project
What risks should the architect be aware of when setting the requirement for a warranty, checking its wording, and ensuring its delivery to the client?
Be aware that in setting the requirement for a warranty, in checking the wording of the warranty offered and in ensuring that the signed warranty agreement is obtained from the contractor and delivered to the client, risk exists to the architect.
Be aware that requesting a warranty also incurs a cost addition to the contract sum and this additional cost included in the tender may not offer value.
What challenge may arise for those pursuing a warranty for building work, especially concerning failures in workmanship?
Many who have tried to pursue a warranty for building work have discovered that, although a manufacturer may back up the product, one must look to the installer for a failure in workmanship. Proving the failure and pursuing the installer may take considerable effort.
What potential consequences might architects face if the installer is of no substance and the client relied on the comfort of the warranty?
If it transpires that the installer is of no substance and the client has relied on the comfort of the warranty, there could well follow accusations that the architect’s design was deficient and/or that the architect “failed to adequately supervise.”
What is the definition of a Warrenty?
A warranty is an undertaking by one party to another (to make good defects in the contract works).
What is the defenition of a guarantee?
A guarantee is an undertaking by a third party in favour of the first party, to act in the event that the second party does not fulfil their obligations under the guarantee (to make good defects in the contract works).
What are some examples of Guarantees in the building industry?
Master Builders New Home and Alterations & Additions 7-year Guarantee Agreement.
This is a true guarantee because in the event of the failure of the contractor, Master Build Services are required to make good (third party)
BuiltIn guarantee used at Apple Shed