At the end of the first iteration, the team finishes user stories A, B, and 50% of C.
Story A = 8 points
Story B = 1 points
Story C = 5 points
Story D = 3 points
What is the team’s velocity?
9
What are two outputs of Iteration Planning?
- Iteration Backlog
When is Iteration Planning completed?
When the team commits.
What are two SAFe primary opportunites for driving relentless improvement?
- Iteration Retrospective
What does SAFe CALMR apply to?
- Culture