Planned Value (PV)
also in Project Cost Mgmt Terms
What the project should be worth
Earned Value (EV)
also in Project Cost Mgmt Terms
What the project is worth
% complete x BAC
Actual Cost (AC)
What the project has spent so far
Cost variance (CV)
also in Project Cost Mgmt Terms
the difference between earned value and the actual value
EV-AC
Positive # = under budget
Negative # = overbudget
Budget at Completion (BAC)
what the project budget is
Schedule variance (SV)
Also in Project Cost Mgmt terms
the difference between earned value and planned value
EV - PV
Positive # = ahead of schedule
Negative # = behind schedule
Variance at Completion (VAC)
Project of being over or under budget based on current performance.
VAC = BAC - EAC
Positive = under budget
Negative = over budget
Cost Performance Index (CPI)
also in Project Cost Mgmt Terms
Shows overall cost efficiency on the project.
CPI = EV / AC
> 1 - under budget
< 1 - over budget
Schedule Performance Index (SPI)
Also in Project Cost Mgmt Terms
Shows overall schedule adherence
SPI = EV / PV
> 1 ahead of schedule
<1 behind schedule
Estimate at Completion (EAC) - Standard formula
also in Project Cost Mgmt Terms
Forecasts final project costs based on current performance
BAC / CPI
Estimate at Completion (EAC) Future work at planned costs formula
also in Project Cost Mgmt Terms
forecasts final project costs based on current performance
AC + BAC - EV
Estimate at Completion (EAC) initial cost estimates flawed
also in Project Cost Mgmt Terms
forecasts final project costs based on current performance.
AC + Estimate for remainder of project
Estimate at Completion (EAC) CPI and SPI affect remainder of project
forecasts final project costs based on curent performance
AC + [BAC-EV / (CPI x SPI)
Estimate to complete
predict how much more the reminder of the project will costs
EAC - AC
TCPI (utilizing BAC)
Predicts likelihood of reaching BAC
(BAC-EV) / (BAC - AC)
> 1 = harder to complete and meet BAC
<1 = easier to complete and meet BAC
TCPI (utilizing EAC)
Predicts likelihood of reaching EAC
(BAC-EV) / (EAC - AC)
> 1 = harder to complete and meet EAC
<1 = easier to complete and meet EAC