10 Old Bond Street: What was the reason you came in so far under budget?
Omitted works:
- Concrete paving slabs replacement not required [couldn’t see on initial inspection due to ductwork blocking view].
- Coping stones re-bedding [repointed instead].
- External lighting repairs not required.
- M&E plant mostly removed by someone else.
- Brickwork repointing reduced [stone repointing increased].
- Doff clean changed to jet wash [acoustic enclosure].
a) How are sub-contracts warrantied?
b) What forms were used?
a) Collateral warranties.
b) JCT form (as a deed).
KI 1: How much more would it cost to go with Option 2 rather than Option 3?
£11,000.
[£5k vs £16k]
KI 1: How much longer would Option 2 have taken versus Option 3?
Around 1 week.
How did you report to the client in terms of project costs?
[Payment certificate:
- Contract sum.
- Certified amounts to date.]
How did you deal with the variation of the works on a contractual basis?
How did you value the variations?
Could the contractor have refused the variation? If so, on what basis?
Yes, based on:
- Quantity [or quality] of the works.
- Changes to the design.
- [Site access].
What would the procurement route be for Old Bond Street?
Why did you use an Intermediate contract rather than MW?
You have stated that you prepared the preliminaries on the project, what did you include in these?
What information did you include in the preambles?
What provisional sums did you include?
What was the tender period?
What did you check regarding the contractor’s insurance?
What were the variations on the project?
Add:
- Stone panels repointing.
- Leadwork to upstands.
- Liquid repairs to platforms.
Omit:
- Concrete paving slabs.
- Coping stones.
- External lighting repairs.
What was your role for releasing the retention at Old Bond Street?
I released 2.5% on PC. [2.5% released when Making Good Certificate issued].
What RIBA stage did you prepare your specification to?
RIBA Stage 4 - Technical Design.
Can you provide an example of an instruction on Old Bond Street?
Note: Liquidated Damages could not be claimed by the client as they had suffered no direct loss. These were set at £5,000 per week in the contract, calculated as the loss suffered by the client from future rent.
How did you ensure the works were built according to the specification?
How was the budget cost calculated?
Note: Liquidated damages sum: £5,000 per week [not required on this project].
What process did you go through to establish whether the time claimed by the contractor was deemed excessive?
Assessed:
- Proposed programme.
- Works run concurrently?
- Critical path.
- Weather-dependant works.