HCS Flashcards

(10 cards)

1
Q

What is the purpose of the hydrogen recombiner building ventilation system?

A

maintain equipment operability, support personnel access, and support recombiner operation during post-LOCA conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What will cause the hydrogen recombiner cubicle inlet damper to auto close?

A

high rad alarm on 3HVZ*RE09A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which of the following describes the normal (standby) arrangement of the hydrogen recombiner?

A

all system isolation valves closed, and are manually opened when recombiner operation is required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What will cause the B hydrogen recombiner positive displacement blower to auto stop?

A

either HVZMOD20B or 3HVZMOD21B not fully open

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When the H2 recombiner equipment room temp reaches its set point of 80 F, which of the following actions occurs?

A

the equipment room ventilation inlet and outlet dampers OPEN and the equipment room exhaust fan STARTS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

With the “A” hydrogen recombiner running, the air blast HX fan breaker trips. Return gas temperature is increasing.

Which of the following directly occurs as a result of return gas temperature exceeding 141F?

A

the radiant heater breaker trips

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How are the hydrogen recombiner containment isolation valves operated when using the installed reach rods?

A

keep the hand wheel pulled out while operating the valve so that the clutch is not overridden

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the maximum flow rate measurement through a hydrogen recombiner that will ensure adequate equipment protection and performance?

A

7.5” H20

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What method is used to maintain the hydrogen recombines in pre-warmed state, ready for start up?

A

the power supply for the radiant heaters is manually switched from 480 VAC to 120 VAC to provide trickle heat to the reaction chamber

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What area(s) of the hydrogen recombiner building are served by the recombiner building air conditioning unit?

A

the lower level control room area of the recombiner building EXCLUDING the recombiner rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly