List the 7 Horizontal Formats
Labor - Direct Labor PM - Permanent Materials EM - Expendable Materials S - Subcontractor EOE - Equipment on Expense RL - Rentals and Service Labor Rental
What is Direct Labour?
Considered to be the most riskest, highest votatile, and hardest to estimate
What is PM?
Permanent Materials
- Materials that can be accurately determined during bid.
What is EM?
Expendable Materials
ex: Slab Footing - won’t be able to know the exact unit numbers until construction
What is Subcontractor?
S - high productivity from subcontractor POV
low productivity from an owner POV due to performance bond. (Low Risk)
What is EOE?
Equipment on Expense
FOG (Fuel, Oil, Grease)
Tires
Small repairs to the machinary
3rd Party Overhaul
What is RL?
Rentals and Service Labor
What is Rentals?
Any type of rentals, writeoff or depreciation
Methods of supplying the equipment to the job such as: