How does ifrs 15 define revenue?
Income arising from e’ ord actvt
What is SCD formula? (steps)
-steps (1-5)
-criteria
-decision
finish with step 5
what are the criteria for step 1? AP^2 RS
Approved
payment = probable
right to both parties
SOF
what are the criteria for step 2? PO
How many PO?
Distinct (check buyer ad seller perspective) // benefit separately or tgt // identifiable or deliver at different POT
what are the criteria for step 3? (5 recog price)
what is criteria for step 4? (allocation)
allocate price to PO based on SASP
what are criteria for step 5?
recog of revenue (satisfy PO/ deliver goods/ transfer control)
satisfy PO:
POT - sale of goods (e’ has control/ developer needs to 100% complete and deliver & trsf control)
POD - cust will recv and consume simultaneously
if construction company: CHECK for POD
-cust has control
-contractor enhance asset
-no alternative use
-enforceable right to recv payment
How to calculate percentage of completion using input method?
cost of work done to date / TEC (cost to date + future est cost to complete) x 100
How to calculate percentage of completion using output method?
value of work done (contract price x %) / contract price x 100
what is SOF in a combi contract?
whether in substance is 1 contract or multiple (substance vs legal)
SINGLE / one contract if met few criteria:
-negotiate as one package with single commercial obj
-amount of consd in one contract depends on price or perf on the other contract
-g/s in each contract are a single PO
what are the types of variation?
modification (clause within contract) and reassessment (no clause found)
how to account for modification of contract (identification)
check!
-distinct/ or single PO
-reflect SASP