Issues in Construction Flashcards

(30 cards)

1
Q

Project Life Cycle

A

Pre-Project Phase
Design Phase
Bidding Phase
Mobilization Phase
Construction Phase
Project Close-Out and Termination Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bid Process

A

Notice to Bidders and Giving of Bid Package
Bid Submission
Bid Opening
Bid Evaluation
Contract Award

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Construction Phase

A

Contract Award
Notice to Proceed
Project Activities
Preliminary Acceptance
Final Acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Issues during Construction

A

Issues related to Site Layout
Time Extensions
Change Orders
Change Conditions
Suspensions, Delay, or Interruption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Job site infrastructure is influenced by aspects of the project such as:

A

Size of Project
Type of Construction
Construction Time Frame
Weather and Environmental Factors
Job Site Topography, and surrounding or adjacent Permanent Infrastructure Constraints
Availability and Tyep of Construction Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Job site aspects which must be analyzed include:

A

Site Drainage
Configuration of Access Roads as well as Transportation Protocols
Location of Hook-ups (connections) for Water, Electricity, Wastewater, etc.
Location and Type of Site Buildings and Structures
Location of Cranes, Hoists, Personal Lifts, and other Major Equipment/Resources
Nature and Location of Storage and Lay Down Areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Increase in project time for acts beyond contractor’s control

A

Time Extension

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Often circumstances beyond the contractor’s control, which could not have been reasonably anticipated at the time of bidding, lead to delays

A

Time Extension

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The owner may extend the term of the contract in the ff cases:
If a contractor is assigned to perform additional works, provided that the period of extension is ___ to the size and nature of the works and the date of assignment

A

proportional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The owner may extend the term of the contract in the ff cases:
If an order is issued by the ___ to suspend the works or part thereof for reasons not attributable to the contractor

A

Government Authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The owner may extend the term of the contract in the ff cases:
If the annual funds allocated for the project are ___ to complete the work within the specified time

A

not sufficient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The owner may extend the term of the contract in the ff cases:
and other reasons deemed reasonable by the ___

A

owner or client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Owner or consultant may order the contractor in writing to modify, add or delete any part of the work

A

Modifications, Additions and Deletions (Change Order)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A condition could not reasonably have been foreseen by the contractor, there would be no allowance for it in his or her bid

A

Changed Condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The failure of the bid documents to reflect this situation would cause the contractor to claim a ___.

A

change condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If the owner accepts the changed condition, the extend scope of work represented will be included in the contract as a ___

17
Q

If the owner does not accept the changed condition claim, the validity of the claim must be established by ___ or ___

A

litigation, arbitration

18
Q

Owner/consultant may order the contractor in writing to suspend, delay or interrupt all or any part of the work for such period of time as may determine to be appropriate for the convenience of the government or any other reasons deemed reasonable by the owner

A

Suspension, Delay or Interruption

19
Q

arbitrary daily delay charges to encourage the contractor to maintain completion schedule

20
Q

justified penalties, that reflect actual loss due to project delay

A

Liquidated Damages

21
Q

During the construction period, the contractor is reimbursed on a ___

A

periodic basis

22
Q

Normally, at the end of each month, the owner’s representative and the contractor jointly make an estimate of the work performed during the month and the owner agrees to pay a ___ to the contractor based on work performed prices

A

progress payment

23
Q

The owner retains or holds back a portion of the total amount due to the contractor as an ___ for the contractor to properly complete the project (Retention)

24
Q

The date when work is certified by the architect to be sufficiently complete as specified in the contract documents.

A

Substantial Completion

25
The owner should be able to occupy the work fully or partially.
Substantial Completion
26
A mutually acceptable date is established when substantial completion appears to have been reached.
Beneficial Occupancy Date
27
On this date, an inspection of the facility is conducted (Punchlist)
Beneficial Occupancy Date
28
The contratcor can handover the project to the owner
Preliminary Handover
29
One year after the preliminary handover when a contractor maintains any material, equipment or workmanship faults.
Warranty Period
30
Signals the completion of contractor contractual obligation
Final Handover