9.1 Explain the purpose, typical content and importance of a procurement strategy
9.2 Differentiate between different methods of supplier reimbursement
9.3 Differentiate between different contractual relationships
One comprehensive contract: The simplest arrangement in which one supplier is responsible for everything required (turn-key or design and construct). The risk involved is that all responsibility is with one supplier.
Sequential contract: The sequential use of two or more contractors during a project. For example, design and then construction. This allows options to be considered before costly work of construction or manufacture. Detailed design can be completed and price before customer is committed to greater costs. However, interaction between the stages must be planned well and it’s hard to know final cost of project int he first stages.
Parallel contract: Where a similar scope of work is given to two or more suppliers and they work in parallel to deliver the completed project. E.g. refurbishment of a multi-storey building where diffeent contractors do each floor. Good if individual suppliers have different capacities and competition can be generated (but management is key so as not to compromise on design or safety).
Subcontracts: A prime contractor holds the contract and then subcontracts it to others to complete (often in parallel). Customer may only have indirect ability to assess and influence so conditions may be necessary for sub-contracting. It also lessens the possibility of pipeline work for suppliers and therefore may lead to poorer performance.
Partnering/Joint Venture: Very large projects are completed by a number of suppliers working together in a partnership. May be necessary if the total work is too large or complex for a single supplier. Often a separate company is set up and each supplier will nominate a director to sit on the board of the joint company.
9.4 Explain a supplier selection process
-