What is meant by “Process Strategy”?
How to produce a product or service that meets or exceeds customer requirements, costs or managerial goals.
What are the 4 basic strategies of “Process Strategy”?
What are the 7 characteristics of “Process Focus”?
Arnold Palmer Hospital
What are the 7 characteristics of “Repetitive Focus”?
Harley-Davidson
What are the 7 characteristics of “Product Focus”?
Frito-Lay
What are the 7 characteristics of “Mass Customization”?
Dell Computers
What is meant by “Linking Manufacturing Processes”?
The idea here is that we use different kinds of Process Strategies to produce a product. Can go from Repetitive Focus to Mass Customization for instance, depending on which part of the product that should be produced.
In terms of Process Strategy, what is meant by “Flexibility”?
Flexibility is the ability to respond with little penalty in time, cost or customer value.
What is meant by “Process Analysis and Design (PAD)”, what are the 4 different methods suggested and how does each of the work?
PAD is about what can we do/ look at in the process in order to make the process shorter or more efficent.
(Definitions taken from different sources)
What are the 8 different methods for “Improving Service Productivity?”
SSP-F-MAST
(taken from slide 27-28)
What is meant by “Capacity”?
Capacity Management can be divided into a long-term and short-term perspective, which ones and what do they mean?
What is “Utilization” and how is it calculated?
Utilization - Is the percent of design capacity actually achieved. How we take use of our input when making our output. Wants this to be as high as possible.
Formula: {Average Output Rate / Maximum Capacity Rate} * 100%.
What is meant by “Design Capacity” and “Effective Capacity”?
Design Capacity: This is the maximum theoretical output of the system.
Effective Capacity: This is the capacity a firm expects to achieve given current operating constraints.
In terms of Capacity, what is meant by “Efficiency”?
This is the percent of effective capacity actually achieved.
Efficiency = Actual output / effective capacity.
In terms of Efficiency, what could happen as the organization becomes larger?
“The larger an organization becomes the more the opportunities for inefficiency opens up” - slide. 36
What is meant by a “Capacity Cushion (CC)”?
The amount of reserve capacity a process uses to handle a sudden increase in demand or temporary losses of production capacity.
Formula: CC = 100% - Average Utilization Rate
In terms of “Capacity Timing and Size” we have mentioned 2 strategies, what’s their name and what do they highlight?
1) Expansionist Strategy: Based on forecasts we exepct and increased demand in the future leading to new capacity being added now to be ready to meet this demand in the future.
2) Wait-and-see Strategy: Here, you want to wait a little bit closer to when the demand is expected to change. Why this is the case is because creating new capacity can be expensive for many firms and this passive approach enables them to get a clearer picture of the future at the cost of losing time of preparations.
In terms of “Theory of Constraints”, what is meant by the following:
1) Throughput time -
2) Cycle time -
3) Takt time -
1) Throughput time - Is the time it takes for a product to go through production from start to end, with no lead time.
2) Cycle time - determines the capacity of a process in sense of how much of a unit/or how many units can be processed during the cycle of a part of the process or the entire process.
3) Takt time - Is the maximum time within which all operations should be completed as to meet the demand.
What is meant by “Theory of Constraints”?
Theory of Constraints is about a systematic management approach that focuses on actively managing those constraints that impede a firm’s progress towards its goal. Handling bottlenecks.
What are the 7 key principles of “Theory of Constraints”?
What is meant by the “Drum-Buffer-Rope”-system?
A planning and control system that regulates the flow of work-in-process materials at the Bottleneck or Constrained Capacity Resource (CCR) in a productive system.
Drum = Bottleneck sets the beat of the process. Buffer = The time of early flows into the bottleneck, protection against disturbance of the flow. Rope = The Bottleneck controls the timing of the release of material in the throughput.