Lecture 6 Flashcards

(41 cards)

1
Q

What does CPM stand for?

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does PERT stand for?

A

Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the definition of a schedule in project management?

A

The conversion of a project action plan into an operation timetable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or False: All project activities need to be scheduled at the same level of detail.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where is most scheduling done in project management?

A

At the WBS level, not the work package level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a critical work package?

A

The most important work packages that may be shown on the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a network in project scheduling?

A

The combination of all activities and events that define a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List three advantages of network scheduling.

A
  • Consistent framework
  • Shows dependencies
  • Determines expected completion date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of PERT?

A

To use probabilistic time estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the main difference between CPM and PERT?

A

CPM uses deterministic time estimates, while PERT uses probabilistic time estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is an activity in project management?

A

A specific task or set of tasks required by the project, using resources and taking time to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Fill in the blank: A ________ is the result of completing one or more activities.

A

Event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does ‘critical path’ refer to in project management?

A

The path through the project where, if any activity is delayed, the project is delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

True or False: There can be more than one critical path in a project.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a sequential activity?

A

An activity that must be completed before the next one can begin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Parallel activity?

A

Activities can take place at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

____ is an activity thaty must be completed just before a particular activity can begin

A

Immediate Predecessor

18
Q

What are the steps to constructing the network

A

Begin with the start activity, add activities without precedence as nodes, add activities that have those activities as precedencies, then continue

19
Q

Who developed Gantt charts

A

Henry L Gantt

20
Q

What is the purpose of Gantt charts?

A

To show planned and actual progress of a project

21
Q

List two advantages of Gantt charts.

A
  • Easily understood
  • Provides a picture of the current state of a project
22
Q

What is a disadvantage of Gantt charts?

A

Difficult to follow complex projects

23
Q

what are three important things to be aware of when estimating activity times

A
  • It is vital to good project management to be meticulously honest in estimating the time required to complete each of the various tasks included in the project
  • No false deadlines
  • Evaluate alternative ways of completing work
24
Q

What are the three time estimates used to calculate activity times?

A
  • Optimistic
  • Pessimistic
  • Most likely
25
what is the formula for the expected time
(a +4m+b)/6
26
variance formula
( (b-a) / 6) ^2
27
standard deviation formula
(b-a) /6
28
z-score formula for a given deadline
z = (D - TE) / stand. dev.
29
what is slack time? Another word for it?
also known as flaot. The amount of time that a task in a project schedule can be delayed without delaying the project's overall completion date.
30
What must be assumed for the variance of a set of activities?
Activities are statistically independent
31
Which is more important, Time or Budget?
no answer, the best way to find out which is more important is to consider both
32
What are Budget related risks
- what factors could increase cost - what could delay funding or payment - what assumptions in your cost estimation are uncertain
33
What is the formula to find expected monetary value (EMV)?
Risk probability x cost impact
34
What are known-unknowns in project risk management?
Build contingency reserves for known-unknowns and allocate management reserves
35
Steps in risk assessment frameworks
1. identify risk factors 2. create risk breakdown structure 3. qualitative risk analysis (questionnairesfor determination the probability and impact). Calculate risk score for determination the ranging if risk factors 4. cost matrix for each category (high, med, low) 5. risk response plan for high priority risks
36
What is the purpose of machine learning in project risk management?
To predict and quantify project risks using past data
37
How does natural language processing (NLP) assist in project risk management?
Detects early risk signals from unstructured text
38
What is the role of reinforcement learning (RL) in project management?
Adapts project plans dynamically to minimize risk exposure
39
What is a AI-driven simulation and digital twin in project management?
tests risk scenarios virtually before real implementation
40
name any 3 limitations in AI
- data quality issues - human factors ignored - model bias - lack of transparency - need for human oversight - high cost/complexity - security risks - overreliance
41
True or False: simulation should be used after understanding traditional statistical approaches.
True