What is the difference between Project Administration and Project Process and Procedures?
Project Administration
Project Process and Procedures
What is insurance?
Insurance is an agreement stating that the insurer will give the insured a benefit (usually financial) if a specified event occurs.
What types of insurances are required in construction projects?
What is All Risks Insurance?
• Insurance of the building works.
• Covers physical loss or damage to works and materials on site.
• This can be taken out by the Contractor or Employer, contract should specify who.
• Contract usually defines this should be taken out in joint names (Employer and Contractor insured under the same policy).
• Covered under Schedule 3 in JCT D&B:
o A: Contractor – All risks.
o B: Employer – All risks.
o C: Employer – insures existing structures and works or extensions to them.
What is Employers Liability Insurance?
What is Public Liability Insurance?
What is Professional Indemnity Insurance?
• Insurance against liability arising from professional negligence, such as breach of a contractual obligation to exercise reasonable skill, care and diligence.
• Will include a limit of indemnity and should be on the ‘each and every claim’ basis. This means that the cover amount is capped for a single claim but multiple claims can be made during the policy with no overall limit (‘in the aggregate’ sets overall limit e.g. £10m limit would be reached with two claims of £5m during the policy duration).
• ‘Claims made’ basis means that the policy in place when the claim is made is engaged, not the policy in place when the works in question were carried out.
• RICS require members to have a minimum of 6 years run off cover due to the ‘Claims made’ basis.
• A copy of the certificate must be sent to the RICS on an annual basis.
• How to get a competitive quote:
o Start renewal process early 6 weeks ahead of date.
o Ensure proposal form demonstrated food risk management policies.
o Ensure the broker understands what you do and how you do it.
Minimum levels of Professional Indemnity Insurance (PII) cover?
The minimum cover is based on turnover:
• Up to £100k -£250k
The cover must be appropriate for the particular type of work and circumstances.
What is a ‘net contribution clause’?
A contract term stating that, where more than one person is liable for the same loss or damage, the contracting party’s liability will be limited to the fair and reasonable amount that a court would apportion against it.
For example if an architect and engineer were jointly responsible for a defect:
A professional consultant may argue that a net contribution clause:
Is fair, whereas the common law position of 100% liability without 100% responsibility is unfair.
Prevents the risk of one professional consultant’s insolvency transferring to another professional consultant (or its insurers).
A client may argue that a net contribution clause:
Seeks to circumvent an established rule of common law.
Transfers insolvency risk to the client, in circumstances where it cannot insure against that risk.
Only ever limits the liability of a party who has already been found to be at fault.
Is not acceptable to a funder providing development finance.
What are excess provisions?
A clause that means the insurer is only liable for the remaining claim amount after all other sources of cover have been claimed against.
How would you client be protected from contractor insolvency?
Performance Bond or Parent Company Guarantee (see Contract Practice).
What types of surveys are required for construction projects?
What is Rights to Light?
What is a Party Wall?
If you intend to carry out building work which involves one of the following categories you must comply with the Party Wall Act (1996):
• Excavating near a neighbouring building.
If the work falls within the Act then all Adjoining Owners must be notified.
When do you need planning permission?
What types of planning application are there?
Local Planning Authority consent and listed building consent from Historic England.
Appeals can take from 20 to 30 weeks.
What is the difference between planning conditions and obligations?
Conditions
Obligations
What are the different types of planning conditions?
What documents are usually included in a full planning submission?
• Plans
o Location plan - development in relation to its surrounding properties.
o Site plan - development in relation to the property boundary.
What is a TPO?
An order made by a local planning authority in England to protect specific trees, groups of trees or woodlands in the interests of amenity.
What is Building Control?
Approved Inspector or District Surveyor (LPA) certifying that a building meets the Building Regulations (Building Act 1984). Guidance on how to achieve these requirements is set out in the Approved Documents.
What are the approved Documents?
16 Documents available on the Planning Portal which demonstrate how to comply with Building Regulations.
A – Structural Safety B – Fire Safety C – Resistance to contaminants and moisture D – Toxic Substances E – Resistance to sound F – Ventilation G – Sanitation, Hot Water Safety and Water Efficiency H – Drainage and waste disposal J – Heat Producing Appliances K – Protection from falling L – Conservation of fuel and power M – Access to and use of buildings N – Glazing; safety P – Electrical safety Q – Security Dwellings 7 – Workmanship and Materials