A legally binding agreement (between two parties) to provide goods and services within a specified timeframe.
Offer Acceptance (or counter offer) Consideration Intention (to be legally bound) Capacity (to make agreement) (e.g. power of attorney on behalf of a company)
Coventry demolition - Liasing with Main contractor to overlap the works, early survey work can begin on site whilst last section of demolition taking place.
N 1. Why use standard forms of contract?
N 2. Why wouldnt you use a bespoke contract?
N 2. Why wouldnt you use a bespoke contract?
N 3. What is required to form a contract?
Offer Acceptance Consideration Capacity Intention Legality?
N 4. What should you consider when selecting the contract?
N 7. What standard forms of contract do you know that are offered by JCT?
N 8. Can you name some NEC standard contract forms?
NEC - Engineering and Construction Contract (ECC)
N 12. When is a JCT Minor Works contract NOT suitable?
N 13. Can you provide more information on the JCT Major project construction contract?
N 14. Can you provide more information on the JCT Design and Build Contract 2011?
N 15. Can you provide more information on the JCT Management Building Contract?
N 16. Can you provide more information on the JCT Construction management contract?
N 17. Can you provide more information on the JCT Prime Cost Building Contract?
N 18. Can you provide more information on the NEC Option A contract?
Priced Contract with an Activity Schedule
N 19. Can you provide further information on the NEC Option B contract?
Priced Contract with a Bill of Quantities
N 20. Can you provide further information on NEC Option C contract?
The NEC Option C is a target cost contract with activity schedule where the out-turn financial risks are shared between the client and the contractor in an agreed proportion
N 21. Can you provide further information on NEC Option D contract?
Option D provides for a target cost with a bill of quantities:
A target cost introduces a mechanism that enables the contractor, and/or the consultant team, to share in the benefits of cost savings, but also to bear some of the cost when there are cost overruns. This is typically shared in a pre-agreed proportion.
Option D includes core and secondary option clauses, the schedules of cost components, and contract data.
N 22. Can you provide further information on NEC Option E contract?
Option E is a cost reimbursable contract
Contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
The financial risk involved is largely taken by the client.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Option E contains the core clauses, secondary option clauses, schedules of cost components, contract data, and so on.